Weekend Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Free BICSI RCDDv14.1 Practice Exam with Questions & Answers | Set: 9

Questions 81

A 3 trade size conduit is sized at

Options:
A.

78 mm (3 in)

B.

91 mm (3 1/2 in)

C.

103 mm (4 in)

D.

129 mm (5 in)

BICSI RCDDv14.1 Premium Access
Questions 82

Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)

Options:
A.

Test reports

B.

Shop drawings

C.

Cost summary

D.

Site survey

E.

Request for information (RFI)

Questions 83

Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

Options:
A.

PERT

B.

Calendar

C.

Milestone

D.

Gantt

Questions 84

A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters

To ensure the realization of long-term benefits what should the program manager use?

Options:
A.

Benefits register

B.

Benefits sustainment plan

C.

Benefits management plan

D.

Benefits transition plan

Questions 85

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.

What should be done with the identified potential risk?

Options:
A.

Incorporate it into the risk register and perform a thorough analysis

B.

Mitigate the risk before it is incorporated into the risk management plan

C.

Document the risk in the program transition plan and identify it as a potential issue

D.

Document it m the issue log and immediately notify the steering committee

Questions 86

To properly size and provide accurate cost estimates for a communications distribution horizontal pathway that will include BAS system infrastructure, the designer should provide ________ for every BAS outlet or device based on total floor area.

Options:
A.

9.30 m2 (100 ft2)

B.

23.20 m2 (250 ft2)

C.

91.40 m2 (300 ft2)

D.

152.40 m2 (500 ft2)

Questions 87

A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase Tracking and reporting of actual benefits realized is one part of the review

What is the other part of the review"?

Options:
A.

Tracking and reporting on benefits management plan

B.

Identifying factors Influencing delivery of benefits

C.

Demonstrating that other stage gate requirements have been met

D.

Gathering additional stakeholders' requirements

Questions 88

In specifying labels and pruned tags that meet Underwriters Laboratories (UL) 969 Standard, marking and labeling systems are provided following the listed metrics. Which two of the following are REQUIRED for the UL standard? (Select two options.)

Options:
A.

Adhesion test

B.

Thickness test

C.

Texture test

D.

Durability test

E.

Visual inspection

Questions 89

A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha's program closure plan?

Options:
A.

Execute the transition plan and Include Knowledge transfer to transition Alpha support to operations

B.

Keep the Alpha program open until support is no longer required, then execute program closure

C.

Adjust Alpha's exit criteria to ensure its support is included in the Beta program

D.

Document the program closure procedure to ensure that resources are released from Alpha to develop Beta

Questions 90

In a PTP network using optical fiber, the ________ is responsible for media conversions from the optical fiber to the balanced twisted pair network within the residence.

Options:
A.

ONU

B.

OS

C.

ONT

D.

OLT

E.

OLTS

Exam Code: RCDDv14.1
Certification Provider: BICSI
Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14.1
Last Update: Jul 12, 2025
Questions: 320