A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
Which service is NOT typical of Grade 1?
The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized
After further analysis of the performance indicators the program manager should do which of the following*?
A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?
In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate reviews.
What should the program manager do next?
The new performance financial system is delivered lo all business entities on time following a one-year implementation program After six months of utilization the global finance department one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies
To address these shortcomings the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?
An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However the business team does not report to the IT program manager and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?
Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?
What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)
Program manager B leaves the program and program manager A takes over the program responsibilities Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?