Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free BICSI RCDDv14 Practice Exam with Questions & Answers | Set: 7

Questions 61

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.

To ensure continued funding for the program, what should the program manager do next?

Options:
A.

Complete the benefits sustainment plan and update the benefits register

B.

Present a revised ROl to the program sponsors based on the remaining investment.

C.

Conduct a cost-benefit analysis to ensure the program sponsors understand the program's long-term benefits

D.

Review the program business case and the program's strategic alignment and long-term benefits with the program governance board.

BICSI RCDDv14 Premium Access
Questions 62

In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?

Options:
A.

Concept Design

B.

Design Development (DD)

C.

Schematic Design (SD)

D.

Construction Document (CD)

Questions 63

A program manager has four projects pending approval Senior management asks the program manager to identity a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision.

Which project should the program manager select to be cancelled?

RCDDv14 Question 63

Options:
A.

Project A

B.

Project B

C.

Project C

D.

Project D

Questions 64

A company CEO meets with key customers to learn how they can be better served Alter discovering that some executive team members disagree with each other, the CEO asks the program management office (PWO) to develop a program to better serve key customers based on their strategic importance to the company's long-term goals.

What should the program manager do to establish and successfully manage the program's direction?

Options:
A.

Create a program strategy to obtain the required funding from the portfolio decision team

B.

Develop and foster relationships with stakeholders to improve communication

C.

Conduct stakeholder interviews to address their concerns and expectations

D.

Identify a list of projects, and then assign them suitable project managers

Questions 65

When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)

Options:
A.

Request a Change Order from the client for the extra work performed.

B.

Document the reviewer's status and/or comments

C.

Review the contract requirements and revise the submittal to comply with these requirements

D.

Request a variance from the contract requirements from the client.

E.

Submit an alternate product in lieu of one that was previously submitted, even if it does not meet all of the contract requirements

Questions 66

The program selection committee presents several programs for approval:

RCDDv14 Question 66

Which program was selected based solely on a three-year return on investment?

Options:
A.

Program A

B.

Program B

C.

Program C

D.

Program D

Questions 67

A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects.

Where should the program manager incorporate this input?

Options:
A.

Program management plan

B.

Stakeholder register

C.

Vendor management matrix

D.

Program risk management plan

Questions 68

Which of the following is a common application for exothermic welding of earthing (grounding) and bonding conductors?

Options:
A.

Bonding to structural steel

B.

Locations requiring monthly maintenance

C.

Connections made to the TBB

D.

Cable to cable connections

Questions 69

Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled

What is your MOST appropriate next step?

Options:
A.

Secure funding from another project that was cancelled

B.

Use an integrated change control process

C.

Use the available management reserve

D.

Advise Company B that funding and resources are not available

Questions 70

Which of the following options BEST describes Request for Quote (RFQ)?

Options:
A.

Usually provides more detail involved with selecting the material, equipment, and components required during implementation (e.g. make, model, performance specifications)

B.

Can be submitted by the contractor in response to a field order or as an uninitiated request for a change in scope

C.

Used to obtain a formal response to the contract documents

D.

An invitation for the design professionals (e g, architect, engineer, consultant) or contractors to submit a proposal for services

Exam Code: RCDDv14
Certification Provider: BICSI
Exam Name: BICSI Registered Communications Distribution Designer – RCDDv14
Last Update: Jul 15, 2025
Questions: 288