Free BICSI RCDDv14.1 Practice Exam with Questions & Answers | Set: 6

Questions 51

Coupling with electrical circuits can create inductive interference to telecommunications facilities. Which of the following can decrease the coupling effect?

Options:
A.

Decrease the exposure length

B.

Make sure that the single-phase components add in phase

C.

Decrease the physical separation

D.

Increase the earth resistance

BICSI RCDDv14.1 Premium Access
Questions 52

A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured

What should the program manager do to address the risk?

Options:
A.

Build a coalition with local companies that can influence the government to renegotiate the imposed deadline

B.

Create fine and closure scenarios to assess the impact on the program and create a contingency plan

C.

Generate a delivery incentive contract with the selected fiscal expert to ensure on-time delivery of the revised financial statements

D.

Assess the risk incorporate it in the program's risk management plan and meet with the steering committee

Questions 53

When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)

Options:
A.

handle only the day one needs as the future is unknown.

B.

minimize occupant disruption when horizontal pathways are accessed.

C.

handle at least 3 different cabling media types.

D.

accommodate cabling changes

E.

accommodate at least 50 percent future growth

Questions 54

ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by

Options:
A.

coordinating with the job site supervisors

B.

issuing an RFI to the General/Prime Contractor

C.

texting or calling the General/Prime Contractor

D.

issuing a Change Order

Questions 55

What is a simplified cone of protection for lightning strikes as it pertains to a structure (building, pole, etc.)?

Options:
A.

43 m (140 ft)

B.

A base diameter equal to the height of the structure

C.

A base radius equal to the height of the structure

D.

50% of the height of the structure in any direction

Questions 56

The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?

Options:
A.

Program governance board

B.

Program management office

C.

Change control board

D.

Project managers on the program

Questions 57

A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.

What should the program manager update first?

Options:
A.

Procurement management plan

B.

Benefits register

C.

Risk register

D.

Benefits management plan

Questions 58

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

Options:
A.

Join project-level issue resolution meetings to accelerate the decision-making process.

B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project

C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting

D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities

Questions 59

The type of apparatus housed in ERs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)

Options:
A.

Cross-connect facilities

B.

Telecommunication’s equipment

C.

Environmental controls

D.

Lighting controls

E.

Building system equipment

Questions 60

What is the FIRST step in quality evolution (focused on physical quality) when developing a quality plan?

Options:
A.

Qualitative risk analysis

B.

Client satisfaction

C.

Conformance

D.

Client value

E.

Quantitative risk analysis

Exam Code: RCDDv14.1