A program manager learns that their company's organizational strategy has changed This change impacts one component project of a program misaligning it with both the program objectives and the new organizational strategy This component project, however, is already 90 percent complete.
What should the program manager do next?
A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations The high-level scope of this transformation encompasses three main areas.
1. The technology area—assessing which technology/tooling should be retained for the target data center
2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services
3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions
You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase
Which document should be present m your business case?
While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years
What is the expected time of delivery?
Exhibit:
A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (American with Disabilities Act) requirement for front reach using a wheelchair. What will be the maximum reachable height or the value of "X"?
Exhibit:
In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?
When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)
What is the PRIMARY reason for considering a physical ting topology for connecting outlying buildings?
PDF + Testing Engine
|
---|
$66 |
Testing Engine
|
---|
$50 |
PDF (Q&A)
|
---|
$42 |
BICSI Free Exams |
---|
![]() |