Weekend Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Free BICSI RCDDv14 Practice Exam with Questions & Answers | Set: 3

Questions 21

What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?

Options:
A.

5

B.

10

C.

12

D.

18

BICSI RCDDv14 Premium Access
Questions 22

What is the air change requirement for a tunnel of 610 m (2000 ft) long with a diameter of 3.4 m (11 ft)?

Options:
A.

One complete air change per hour

B.

Two complete air changes per hour

C.

Three complete air changes per hour

D.

Four complete air changes per hour

E.

Five complete air changes per hour

Questions 23

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this project manager?

Options:
A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions

D.

Create an online message board so team members can see and respond to everyone's ideas

Questions 24

A sponsor decides that the business environment is unfavorable for continuation of a program.

The sponsor asks that the program be closed.

What items should be completed as part of the program's final report?

Options:
A.

Lessons learned, successes and failures, and financial and performance assessments

B.

Final updates to the benefits register, successes and failures, and resource disposition

C.

Financial and performance assessments, successes and failures, and reason(s) for program closure

D.

Knowledge transition, successes and failures, and reason(s) for program closure

Questions 25

In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?

Options:
A.

0.2 sq m (2 sq ft)

B.

0.5 sq m (5 sq ft)

C.

1 sq m (10 sq ft)

D.

1.5 sq m (16 sq ft)

E.

2 sq m (20 sq ft)

Questions 26

The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager must prepare the cash flow analysis

Which of the following should be considered to get a baseline budget?

Options:
A.

Currency exchange rates

B.

Component cost estimates

C.

Baseline schedule

D.

Program payment schedules

Questions 27

When should a program manager approve the closure of a component project?

Options:
A.

When acceptance criteria of the project are met

B.

When the project has delivered the protect benefits

C.

When program deliverables are complete

D.

When project deliverables are complete

Questions 28

A company is evaluating the implementation of enterprise resource planning (ERP) software.

The program manager performs an analysis to confirm the program's feasibility

What other important step should the program manager complete^

Options:
A.

Development of the program's vision statement

B.

Review of strategic goals against any external environmental factors

C.

Identification and documentation of the initial risks for ERP software Implementation

D.

Mapping of the financial benefits to the ERP software's functionality

Questions 29

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule The program manager now perceives significantly more risk to the larger program due to this delay.

What should the program manager do to address this risk with the program sponsor and governance board?

Options:
A.

Share the concerns with the program sponsor to confirm understanding of the new development Next, update the program budget, implementation plan, and risk management plan for governance board approval

B.

Update the component project's risk register, issue log, implementation plan, and risk management plan next, meet with the program sponsor to revise the program budget. Implementation plan, and risk management plan for governance board approval

C.

Revise the program budget and Implement the component project by managing It closely to recover the month-long delay Next, update the component's project and risk management plans for governance board approval

D.

Update the program budget, and task the component project manager with implementing the plan next, submit a change order for approval to apply more resources to reduce the larger program's risk profile

Questions 30

The new performance financial system is delivered lo all business entities on time following a one-year implementation program After six months of utilization the global finance department one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies

To address these shortcomings the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?

Options:
A.

Benefits sustainment plan

B.

Benefits governance plan

C.

Benefits realization report

D.

Benefits transition plan

Exam Code: RCDDv14
Certification Provider: BICSI
Exam Name: BICSI Registered Communications Distribution Designer – RCDDv14
Last Update: Jul 12, 2025
Questions: 288