Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free BCS ISEB-PM1 Practice Exam with Questions & Answers | Set: 7

Questions 91

A project manager has limited authority in which type of organizational structure?

Options:
A.

Weak matrix

B.

Functional

C.

Balanced matrix

D.

Projectized

BCS ISEB-PM1 Premium Access
Questions 92

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days.

What should be your concern?

Options:
A.

There is a cost under run.

B.

There is a cost overrun.

C.

May not meet deadline.

D.

The project is 20 days behind schedule.

Questions 93

A project manager has just been assigned to a new project and has been given the approved project charter. The FIRST thing the project manager must do is:

Options:
A.

Create a project scope statement.

B.

Confirm that all the stakeholders have had input to the scope.

C.

Analyze project risk.

D.

Begin work on a project management plan.

Questions 94

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:

Actual cost = $50,000 Plan cost = $45,000 Earned value = $40,000

What is the cost performance index?

Options:
A.

0.80

B.

0.89

C.

1.13

D.

1.25

Questions 95

What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

Options:
A.

Idle resources

B.

Negative float

C.

Lots of free float

D.

Positive float

Questions 96

Which schedule development tool and technique produces a theoretical early start date and late start date?

Options:
A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Questions 97

During the opening rounds of contract negotiation, the other party uses a fait accompli tactic. Which of the following statements is true about fait accompli tactics?

Options:
A.

One party claims the issue under discussion was documented and accepted as part of ScopeVerification.

B.

One party claims the issue under discussion has already been decided and can't be changed.

C.

One party claims to accept the offer of the other party, provided a contract change request is submitted describing the offer in detail.

D.

One party agrees to accept the offer of the other party but secretly knows they will bring the issue back up at a later time.

Questions 98

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?

Options:
A.

Under budget and behind schedule

B.

Over budget and ahead of schedule

C.

Under budget and ahead of schedule

D.

Over budget and behind schedule

Questions 99

Which process group establishes the total scope of a project?

Options:
A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Questions 100

Which of the following tools or techniques is used for Estimate Activity Duration?

Options:
A.

Critical path

B.

Rolling Wave

C.

PDM

D.

Parametric

Questions 101

Which of the following is a Process Group?

Options:
A.

Scoping

B.

Budgeting

C.

Closing

D.

Quality

Questions 102

Which of the following equations is used to calculate cost variance?

Options:
A.

EV-AC

B.

AC-EV

C.

AC+EV

D.

AC/EV

Questions 103

Which of the following is an output of the Information Distribution Process?

Options:
A.

Project calendar

B.

Communication management plan

C.

Requested changes

D.

Communication requirement plan

E.

Organizational Process Assets Updates

Questions 104

Which of the following is an output of Define Scope?

Options:
A.

Project document updates

B.

Project management plan

C.

Scope baseline

D.

Product analysis

Questions 105

What defines the portion of work included in a contract for items being purchased or acquired?

Options:
A.

Procurement management plan

B.

Evaluation criteria

C.

Work Breakdown Structure (WBS)

D.

Contract Statement of Work (SOW)