Free BCS ISEB-PM1 Practice Exam with Questions & Answers | Set: 6

Questions 76

The use of group creativity techniques as a tool and technique is done in which of the following processes?

Options:
A.

Plan Quality

B.

Collect Requirements

C.

Define Scope

D.

Perform Quality Control

BCS ISEB-PM1 Premium Access
Questions 77

Which of the following is one of the tools and techniques for the Define Activities process?

Options:
A.

Rolling wave planning

B.

Dependency determination

C.

Schedule network template

D.

Applying leads and lags

Questions 78

Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide to use ___________________.

Options:
A.

parametric modeling techniques

B.

analogous estimating techniques

C.

bottom-up estimating techniques

D.

computerized modeling techniques

Questions 79

What is the status of the project whose data is shown in the following S-curve?

Options:
A.

Under budget and ahead of schedule

B.

Over budget and behind schedule

C.

Over budget and ahead of schedule

D.

Under budget and behind schedule

Questions 80

Total funding requirements and periodic funding requirements are derived from:

Options:
A.

funding limit reconciliation

B.

scope baseline

C.

activity cost estimates.

D.

cost baseline.

Questions 81

Which contract type is typically used whenever the seller's performance period spans a considerable period of years?

Options:
A.

Fixed-Price-Incentive-Fee contracts (FPIF)

B.

Fixed Price with Economic Price Adjustment contracts (FP-EPA)

C.

Cost-Plus-Fixed-Fee contracts (CPFF)

D.

Time and Material contracts (T&M)

Questions 82

The following reports are normally developed during the project closure phase?

Options:
A.

None of the other alternatives apply

B.

Communications Management Plan and Lessons Learned

C.

Records Archive, Closure Report, & Specifications Document

D.

Records Archive, Closure Report, lessons learned & Formal Acceptance Report

E.

Communications Management Plan and Closure report

Questions 83

All of the following are inputs to the quality process EXCEPT:

Options:
A.

Organizational process assets.

B.

Checklists.

C.

Quality policy.

D.

The project scope statement.

Questions 84

Which of the following is an example of a tool used in Plan Quality?

Options:
A.

Fishbone diagram

B.

Quality audit

C.

Cause and effect diagram

D.

Benchmarking

Questions 85

Job descriptions are examples of ______communications.

Options:
A.

horizontal

B.

downward

C.

diagonal

D.

upward

E.

None of the other alternatives apply

Questions 86

In which of the following contract types is a price ceiling set and any additional costs above the price ceiling becomes the responsibility of the performing organization?

Options:
A.

Firm-Fixed-Price Contracts (FFP)

B.

Fixed-Price-Incentive-Fee Contracts (FPIF)

C.

Cost-Reimbursable Contracts

D.

Time and Materials Contracts (T&M)

Questions 87

The project charter is developed by:

Options:
A.

the customer

B.

senior management and the project manager

C.

senior management

D.

None of the other alternatives apply

E.

the project manager

Questions 88

: 560

Which schedule format usually shows both the project network logic and the project’s critical path

Options:
A.

schedule activities with activity date information?

B.

Schedule table

C.

Schedule network diagram

D.

Bar chart

E.

Milestone chart

Questions 89

Decomposition is a tool and technique used in which of the following?

Options:
A.

Define Scope and Define Activities

B.

Collect Requirements and Estimate Activity Resources

C.

Create WBS and Define Activities

D.

Create WBS and Estimate Activity Duration

Questions 90

Which of the following equations is used to calculate schedule variance?

Options:
A.

EV/PV

B.

PV/EV

C.

EV-PV

D.

PV-EV