Which of the following is the definition of a project?

Options:
A.

Temporary endeavor undertaken to create a temporary business process or product

B.

Temporary endeavor undertaken to create a unique product, service, or result

C.

Permanent endeavor that produces repetitive outputs

D.

Temporary endeavor that produces repetitive outputs

BCS ISEB-PM1 Premium Access
Questions 32

Which one of the following is not an acquisition method?

Options:
A.

negotiation

B.

invitation

C.

purchase

D.

advertising

E.

all are acquisition methods

Questions 33

If a project manager is using observation and conversation to help control the project, she must be involved in which process?

Options:
A.

Develop Project Team

B.

Distribute Information

C.

Manage Stakeholder Expectations

D.

Manage Project Team

Questions 34

What is the tool and technique used to request seller responses?

Options:
A.

Procurement documents

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Questions 35

Which type of tool would be used for the quality planning activity?

Options:
A.

Schedule Analysis

B.

Checklist Analysis

C.

Assumption Analysis

D.

Cost-Benefit Analysis

Questions 36

What is included in a control chart?

Options:
A.

Baseline

B.

Planned value

C.

Upper specification limit

D.

Expenditure

Questions 37

Which of the following is NOT part of stakeholder's management?

Options:
A.

Identify stakeholder's need

B.

make sure all the stakeholders are in project plan

C.

Identify stakeholders

D.

make sure all the stakeholders are in communication plan

Questions 38

If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following?

Options:
A.

The activity will take from 464 to 536 days.

B.

The activity will take from 494 to 506 days.

C.

The activity will take from 476 to 524 days.

D.

The activity will take from 488 to 512 days.

Questions 39

Earned value measurement is an example of:

Options:
A.

Performance reporting.

B.

Planning control.

C.

Ishikawa diagrams.

D.

Integrating the project components into a whole.

Questions 40

Which of the following is TRUE about most project life cycles?

Options:
A.

Staffing level is highest at the start.

B.

The stakeholders' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Questions 41

The scope management plan is a subsidiary of which project document?

Options:
A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Questions 42

What are three basic types of project phase-to-phase relationships?

Options:
A.

Sequential, Overlapping, Non-overlapping

B.

Sequential, Iterative, Overlapping

C.

Sequential, Non-overlapping, Iterative

D.

Iterative, Overlapping, Non-overlapping

Questions 43

Taking out insurance in relation to risk management is called what?

Options:
A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Questions 44

Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?

Options:
A.

Monitor and Control Project Work

B.

Direct and Manage Project Execution

C.

Monitor and Control Risk

D.

Perform Integrated Change Control

Questions 45

Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:
A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management