Which of the following would be considered as a valid objective for the post project review?

Options:
A.

Plan the next project for the project team.

B.

Make proposals for the operation of the project deliverables.

C.

Improve future estimating accuracy.

D.

Plan how to complete the objectives of the project.

APM APM-PFQ Premium Access
Questions 112

What is the main reason for having an extended life cycle?

Options:
A.

Allow the project to have extra time to ensure that that there is enough capacity to realise benefits.

B.

Allow upfront planning for any supplemental activities and incorporate additional considerations for benefits realisation.

C.

Allow time for stakeholders to decide how they will use the output to best effect that will realise benefits.

D.

Allow extra funding to be applied to the project to ensure that sufficient resources exist to maximise benefits realisation.

Questions 113

Which of the following can be adjusted in a timebox situation?

Options:
A.

Deadline and duration.

B.

Time and cost.

C.

Scope and quality.

D.

Budget and resources.

Questions 114

Portfolio management involves:

1) selection

2) control

3) prioritisation

4) transition

Options:
A.

1, 2 and 3

B.

1, 2 and 4

C.

2, 3 and 4

D.

1, 3 and 4

Questions 115

Which one of the following would be expected to form the main part of a risk analysis?

Options:
A.

Deciding on the approach to project risk management.

B.

Evaluating the risk in terms of severity and relative importance.

C.

Deciding on how to respond to the risk and who should implement the response.

D.

Deciding if the risk is a threat or opportunity.

Questions 116

Which one of the following statements about the project risk register is false?

Options:
A.

It facilitates the review and monitoring of risks.

B.

It facilitates the risk appetite.

C.

It facilitates the recording of risk responses.

D.

It facilitates the recording of risks.

Questions 117

Scheduling can best be defined as the process used to determine:

Options:
A.

overall project duration.

B.

project cost.

C.

the project management plan.

D.

sub-contractor's responsibilities

Questions 118

One of the reasons a project life cycle is split into phases is to:

Options:
A.

facilitate formal go/no-go decision making during the project.

B.

balance the costs of work in each phase of project development.

C.

mirror the major deployments of resources throughout the project.

D.

chunk work into time periods of similar durations.

Questions 119

What is the main reason for an initial high-level review of a change request?

Options:
A.

To consider if the change is feasible to evaluate at this stage.

B.

To establish who might be the best stakeholders to be involved in the change.

C.

To ensure that the change request is considered as soon as possible.

D.

To implement the necessary actions to ensure the change has a smooth implementation.

Questions 120

The deployment baseline is the ______ for progress monitoring.

Options:
A.

decision gate.

B.

starting point.

C.

end point.

D.

outline schedule.