A building in a rural area with an FAR of 1.7 is planning to pursue a point under SSc2: Accessible Outdoor Space. Which of the following criteria will help the project achieve the credit?
A project team develops a site plan for a school project with an athletic field and a playground with real grass. In order to qualify for the Water Efficiency Prerequisite, Outdoor Water Use Reduction, the landscape area calculations:
Which of the following are all considered regular building occupants?
When designing a new building, which of the following strategies can be implemented to accommodate future integration of alternative water sources?
A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles. What action must the project take to meet the Option 2 requirements?
A topographic assessment of a project site located 150 ft. (45 m) from a water body was conducted. The results of the slope analysis show that the site is generally sloping 6% to 8% to the northwest over most of the site, with some steep slopes located at the eastern edge of the property, which may impact the runoff volume. Which one of the following LEED credits or prerequisites will be affected by these results?
The design team for a school project finds that they can achieve an 18% savings in indoor water use from the baseline. If the team adds a rainwater harvesting system that reduces water use by another 10%, they can earn:
A developer is considering an urban infill site for a new commercial building rather than a rural greenfield site adjacent to a stream. Which of the following is an economic advantage of the infill site?
A project team is attempting Location and Transportation Credit: High Priority Site and selects Option 1: Historic District. To demonstrate that the project is located in an infill site, the project team must confirm that:
For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include
|
PDF + Testing Engine
|
|---|
|
$41.25 |
|
Testing Engine
|
|---|
|
$31.25 |
|
PDF (Q&A)
|
|---|
|
$26.25 |
USGBC Free Exams |
|---|
|