Free USGBC LEED-AP-BD+C Practice Exam with Questions & Answers | Set: 12

Questions 111

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

Options:
A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

USGBC LEED-AP-BD+C Premium Access
Questions 112

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following must be included in the Basis of Design (BOD)?

Options:
A.

Training requirements

B.

Allowable tolerance for facility operations

C.

Facility, system and assembly performance assumptions

D.

Environmental, energy efficiency and sustainability goals

Questions 113

Which of the following innovation proposals is most likely to be successful to achieve an Innovation Credit?

Options:
A.

Providing an educational program on the environmental and human health benefits of green building practices

B.

Including locked, indoor bicycle storage for 100% of project occupants

C.

Being located next to a 20 mi. (32 km) award-winning bicycle trail

D.

Distributing leaflets to project occupants about available public transit services nearby

Questions 114

A project includes an automatic transfer switch and controls that enable the building’s on-site renewable-energy systems, energy storage, and critical equipment to operate during a power outage. What is this capability called?

Options:
A.

Load management

B.

Islanding

C.

Demand response

Questions 115

What is the minimum percentage of gross floor area that must be complete for a project to use LEED BD+C: New Construction and Major Renovations?

Options:
A.

40%

B.

100%

C.

60%

Questions 116

What phase of the integrative process gives the team the greatest chance of success in meeting the project's environmental goals cost-effectively?

Options:
A.

Design

B.

Discovery

C.

Operations

D.

Construction

Questions 117

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?

Options:
A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

Questions 118

What type of project would benefit from showing compliance with Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

Options:
A.

One in which the budget and timeline would benefit from simplified decision making and analysis during the project design

B.

One in which the project team wants to explore the energy performance and load reduction effects of several envelope and lighting designs and mechanical systems

C.

One in which the project team wants to achieve efficiency trade-offs between systems, offsetting the lower efficiency of one system by the improved efficiency of another

One in which the owner wants an estimate of the carbon reductions or lower operating costs (energy savings, demand charge savings) from energy strategies, beyond a simple calculation for individual energy conservation measures

Questions 119

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

Options:
A.

Retail

B.

Schools

C.

Healthcare

D.

Core and Shell

Questions 120

Landscape irrigation practices consume large quantities of potable water. By evaluating the project's outdoor water budget and irrigation water demand early in the design process in Water Efficiency Prerequisite, Outdoor Water Use Reduction project teams will be able to

Options:
A.

earn Water Efficiency Credit, Water Metering

B.

earn Sustainable Sites Credit, Rainwater Management

C.

estimate and optimize water use in landscape designs

D.

estimate and optimize water use in outdoor fountains and pools

USGBC Related Exams

How to pass USGBC LEED-Green-Associate - LEED Green Associate GAFRE Exam (LEED GA) Exam
How to pass USGBC LEED-AP-O+M - LEED AP Operations + Maintenance (LEED AP O+M) Exam
How to pass USGBC LEED-AP-ID+C - LEED AP Interior Design + Construction (LEED AP ID+C) V4 Exam
How to pass USGBC LEED-AP-ND - LEED AP Neighborhood Development (LEED ND) Exam
How to pass USGBC LEED-AP-Homes - LEED AP Homes (Residential) Exam Exam

USGBC Free Exams

USGBC Free Exams
Enhance your USGBC exam prep with free resources and practice tests from Examstrack. Achieve USGBC certification success by exploring Examstrack.