A business analyst (BA) has developed requirements for a project containing sensitive information. The requirements were approved and the solution was implemented. What should the BA do to ensure these requirements are maintained for future reference?

Options:
A.

Print the requirements package and distribute it to stakeholders in person

B.

Archive the requirements package in the business analysis portal

C.

Store the requirements package on secure shared drive

D.

Send the requirements package to stakeholder in a password protected email

IIBA CCBA Premium Access
Questions 92

After an initial project kick-off meeting, the business analyst (BA) determined that the project has a short deadline and a regulatory mandate with stiff penalties for non-compliance. The stakeholders do not want to risk missing the deadline, and management is willing to commit any amount of resources to meet the deadline. Which kind of approach is suitable for the initiative?

Options:
A.

Crystal clear development process

B.

Kanban development process

C.

Predictive development process

D.

Adaptive development process

Questions 93

While gathering information during a requirements workshop, a subject matter expert states that it is likely that an organizational restructure will occur in one of the business departments that will be utilizing parts of the new system. As such, the business analyst (BA) should:

Options:
A.

ask the project sponsor to confirm whether and when the restructure will occur.

B.

record a risk that requirements may change and further explore the likelihood and impact of the risk.

C.

note the constraint that the solution must be flexible to accommodate different roles after implementation.

D.

proceed as if the business unit will not be restructured and wait for the organization to confirm otherwise.

Questions 94

The project manager has tasked the business analyst (BA) to collect a performance measure on the solution implemented in the latest release. Which of the following considerations can help the BA obtain that information?

Options:
A.

Sample size

B.

Solution size

C.

Performance variance

D.

Risk assessment

Questions 95

A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?

Options:
A.

Quality control checklist

B.

Communication plan

C.

Decision analysis

D.

Risk review

Questions 96

A new regulation results in organizations needing to change online contractual wording. A business analyst (BA) has elicited the requirements and documented them in a change control request Where will the BA find out which stakeholder has the authority to approve, deny, or defer the change request?

Options:
A.

Information management approach

B.

Governance approach

C.

Business analysis approach

D.

Stakeholder engagement approach

Questions 97

A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change. Which factor will the BA need to consider?

Options:
A.

Number of systems being affected by the requirement

B.

Original source of the requirement

C.

Method of requirement communication

D.

Selection of the elicitation for the requirement

Questions 98

A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?

Options:
A.

Confirm elicitation results

B.

Gain agreement on commitments

C.

Monitor stakeholder engagement

D.

Plan stakeholder engagement

Questions 99

The human resources department of an organization needs a new report. The business analyst (BA) assigned to this effort has scheduled a requirements workshop with the users. Users from the legal department have also been invited to the workshop. As the BA sets up the workshop, what can be done in advance to ensure a productive and focused workshop?

Options:
A.

Document the feedback

B.

Facilitate the workshop

C.

Create an agenda

D.

Reserve a location

Questions 100

A business analyst (BA) is developing requirements for a project with a limited budget. The business owner will be prioritizing requirements so that low value requirements can be de-scoped and the project remain within budget. Which of the following should the BA take into account to facilitate prioritization and ensure business objectives are met?

Options:
A.

Data flow

B.

Functional decomposition

C.

Traceability

D.

Dependencies

Questions 101

A business analyst (BA) collected scanned notes, documents, and photos of whiteboards showing the results of a workshop pertaining to an accounting system replacement. What is the BA's next course of action?

Options:
A.

Meet with stakeholders to review the information sent

B.

Meet with a corporate accounting user

C.

Manage stakeholder collaboration

D.

Develop a business analysis information package

Questions 102

The business analyst (BA) has an item logged in the action items register requiring the verification of forthcoming legislation in the next 3 months that might have an impact on the proposed architecture. What should the BA do next?

Options:
A.

Transfer the item to the legal department

B.

Determine the performance measures

C.

Assess the impact immediately

D.

Present the item to the project manager

Questions 103

A business analyst (BA) spent three months eliciting, specifying, and modelling the detailed stakeholder and solution requirements. Right before requirement sign-off, the BA realized that the Vice President was unable to approve the requirements and the Chief Financial Officer should do so. What element of requirement approval did the BA miss?

Options:
A.

Manage conflicts and issues

B.

Track and communicate approval

C.

Gain consensus

D.

Understand stakeholder roles

Questions 104

A business analyst (BA) elicits requirements from end users for a new application, and then completes a set of use cases and use case scenarios. What should the BA do next?

Options:
A.

Identify all the roles and responsibilities

B.

Review the use case scenarios

C.

Conduct a requirements workshop

D.

Create acceptance and evaluation

Questions 105

A business analyst (BA) decided to capture requirements by inviting all the stakeholders to meet at an office location. After invitations were sent, it turned out that not everyone could attend this meeting because of their individual dispersed locations.

Which of the following does the BA need to adjust to handle this situation?

Options:
A.

Project stakeholders

B.

Logistics setup

C.

Elicitation scope

D.

Elicitation technique