Free IIBA CCBA Practice Exam with Questions & Answers | Set: 5

Questions 61

A business analyst (BA) is preparing the elicitation activity plan for a project. How will understanding the elicitation scope assist the BA with the elicitation activity?

Options:
A.

By ensuring the requirements are validated in time

B.

By demonstrating how to record elicitation results

C.

By outlining the level of stakeholder collaboration

D.

By determining when elicitation is complete

IIBA CCBA Premium Access
Questions 62

A business analyst (BA) is developing the requirements for an inventory management system. Some current accounting processes are automated but other departments like purchasing, marketing, sales and distribution departments work in isolation and have a manual process. They extensively use spreadsheets to maintain the transactions and at the end of the day the department managers manually verify and reconcile transactions before supplying the information to the accounting department. In order to verify and validate the elicited requirements, the BA will need to prepare a:

Options:
A.

single process model on automation for all stakeholders.

B.

database structure in the viewpoint of the selected stakeholders

C.

list of requirements in a spreadsheet for all stakeholders.

D.

set of process models in the viewpoint of the selected stakeholders.

Questions 63

A business analyst (BA) has just started a large project and is collaborating with stakeholders to define requirements. Another BA is joining soon to help with this initiative. What action should the BA take to ensure that the new BA understands the project?

Options:
A.

Delay elicitation activities until the new BA joins

B.

Run elicitation sessions in parallel to speed up the process

C.

Ask the new BA to define the stakeholder engagement approach

D.

Document outcomes of discussions with stakeholders

Questions 64

A business analyst (BA) is informing stakeholders about the importance of quality when eliciting requirements. What characteristic describes a quality requirement?

Options:
A.

Simplistic

B.

Consistent

C.

Critical

D.

Functional

Questions 65

A business analyst (BA) is tasked with designing a method of ensuring that the requirements captured during the elicitation sessions satisfy the needs and expectations of the customer experience, within an initiative. The BA identifies a way that the stakeholder requirements can be structured to ensure realization of the desired customer experience. Which viewpoint describes the approach taken by the BA to structure the requirements?

Options:
A.

User interactions

B.

Business model

C.

Audit and security

D.

Business process model

Questions 66

A company is embarking on a software project in a heavily regulated domain. The client expects large upfront planning and detailed documentation for the project. The recommended approach for the project will be:

Options:
A.

adaptive.

B.

predictive.

C.

waterfall.

D.

scrum.

Questions 67

A project aiming at improving an organization's Net Promoter Score is nearing completion. The business analyst (BA) and stakeholders are evaluating ways to measure the performance of the solution. Which technique may be employed?

Options:
A.

Vendor assessment

B.

Market analysis

C.

Focus groups

D.

Business case

Questions 68

A business analyst (BA) creates the following diagram as part of current state analysis activities.

CCBA Question 68

What does a diagram of this type help users to understand?

Options:
A.

Decision-making

B.

Regulatory compliance

C.

Business capability

D.

Process improvement

Questions 69

A company wants to increase its market share in the industry and its Board has prioritized capabilities that need to be implemented to achieve the goal. The business requirements for the top priority were signed off and the solution design has been completed. Due to technical constraints, it is not feasible to implement all the requirements at the same time. What must the business analyst (BA) do to deal with this situation?

Options:
A.

Redefine the business requirements associated with each implementation

B.

Recommend a reduction in the project scope

C.

Allocate requirements to different releases

D.

Ensure all requirements are traceable using a matrix

Questions 70

A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?

Options:
A.

Compare a solution used at another company

B.

Identify the performance objectives

C.

Select performance measures

D.

Determine the reporting requirements

Questions 71

The business analyst (BA) has documented the requirements for a new system and is preparing the requirements for approval. Which of the following helps ensure that requirements are fully understood and traceable?

Options:
A.

Requirements are extracted for review

B.

Requirements are properly classified

C.

Requirements are validated

D.

Requirements meet regulatory standards

Questions 72

During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project's scope. The business analyst (BA) facilitating the workshop should:

Options:
A.

note the issue in the Issue Register to be considered by the Project Manager.

B.

ignore the stakeholder's comment and proceed with the agenda.

C.

consider the issue's impact on the project and gain agreement with stakeholders on the next step.

D.

request the stakeholder to explain the issue further so that possible solutions can be discussed.

Questions 73

The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?

Options:
A.

Create a process model

B.

Develop a work breakdown structure

C.

Build an entity-relationship diagram

D.

Construct a decision tree

Questions 74

During a senior management meeting about a project at the requirements analysis stage, a business analyst (BA) stated that there were a number of workarounds associated with the current application. The Chief Information Officer (CIO) was looking for ways to improve the situation and the BA suggests a solution. Which of the following can the BA suggest that the organization consider to increase efficiencies?

Options:
A.

Process improvement

B.

Strategy realignment

C.

Capability assessment

D.

Project abandonment

Questions 75

A project to replace a financial system uses a waterfall methodology. Initially, meetings with the project subject

matter experts (SMEs) were positive. As the project progressed through the requirements and design phases, the SMEs attended fewer meetings, resulting in a delay to the project build phase. What should the business analyst (BA) have done to prevent the delay?

Options:
A.

Selected a different project methodology

B.

Requested new SMEs participate in the project

C.

Modified the governance structure

D.

Engaged in consistent collaboration