Questions 181

A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?

Options:
A.

Ensure requirements are traceable up to user acceptance testing.

B.

Reassure the project sponsor that testing will be conducted diligently.

C.

Determine the communication plan for requirements.

D.

Compare requirements with compliance requirements.

IIBA CCBA Premium Access
Questions 182

A business analyst (BA) held a formal walkthrough of requirements developed on a project. Stakeholders expressed concerns because they had different interpretations of the requirements. What activity would help ensure a common understanding?

Options:
A.

Ensure compliance with key performance indicators

B.

Ensure consistent referencing of requirements

C.

Ensure correct terminology is used

D.

Ensure appropriate templates are used throughout elicitation

Questions 183

An organization is planning to launch an exciting new service that has never been offered before. The expectations are that the service will be extremely popular with young families, but because the organization wants to keep it a secret until launch day, there is no way of knowing whether this is correct. Why should the business analyst (BA) suggest identifying high customer demand by young families as a risk?

Options:
A.

To manage the associated risks.

B.

To prove the idea is correct.

C.

To provide a benchmark against future change.

D.

To assess the costs and benefits accurately.

Questions 184

A business analyst (BA) has been tasked with examining and analyzing the relationship between a set of requirements by verifying that they are unambiguous. What will the BA be looking for?

Options:
A.

That the relationship is necessary for understanding the requirements holistically.

B.

That relationships are described in the same way, using the same set of standard descriptions.

C.

That there is a genuine relationship and that the type of relationship is described.

D.

That there are no relationships that link elements in two different and conflicting ways.

Questions 185

A Chief Information Officer (CIO) was discussing a solution approach for a technology project in a meeting where a business analyst (BA) was also present. Stakeholders were discussing advantages and disadvantages of each solution approach. What should be the top priority for the BA in assessing the solution approach?

Options:
A.

The strategic design options

B.

The trade-off and value to stakeholders

C.

The strategic alignment with the balanced scorecard

D.

The total cost of ownership of the project

Questions 186

A business analyst (BA) spent three months eliciting, specifying, and modeling the detailed stakeholder and solution requirements. Right before requirement sign-off, the BA realized that the Vice President was unable to approve the requirements and the Chief Financial Officer should do so. What element of requirement approval did the BA miss?

Options:
A.

Understand stakeholder roles

B.

Track and communicate approval

C.

Manage conflicts and issues

D.

Gain consensus

Questions 187

A business analyst (BA) is eliciting requirements for a pharmaceutical distribution company with an expansion plan across many states, each with its own tools and methods. To make the requirements as reusable as possible, what should the BA do?

Options:
A.

Describe the requirements at a high level of abstraction.

B.

Provide details for the requirements.

C.

Limit the relationships between requirements.

D.

Make specific references to applications or departments.

Questions 188

A company wants to increase transaction service offerings using its online channels. The existing application already has some of the required functionality. A new project has been initiated to implement the additional capabilities, but the company management is unsure of the complexity of the project. What exercise must be carried out to determine the changes needed in the new application?

Options:
A.

Perform gap analysis of current and future states

B.

Evaluate competitor applications

C.

Assess organizational culture

D.

Identify internal solution component dependencies

Questions 189

The Chief Executive Officer (CEO) of a company presents a new corporate strategy that will introduce a new system to the organization. The CEO has expressed a concern about the impact on staff once the strategy has been implemented. What must the business analyst (BA) do to address the concerns of the CEO?

Options:
A.

Perform a cost-benefit analysis of the strategy

B.

Ensure requirements are easily accessible

C.

Identify required cultural changes

D.

Align the new capabilities to the company's architecture

Questions 190

A business analyst (BA) is given an additional requirement near the end of the development phase that needs to be incorporated into the system as part of the same release. In this situation, the first activity the BA performs to understand the effect of the proposed change is to:

Options:
A.

Check with the project manager for timeline and budget metrics.

B.

Determine whether stakeholders are available for further elicitation.

C.

Determine whether the additional requirement is traceable to a need.

D.

Consult with the technical team for technical feasibility.

Questions 191

A business analyst (BA) has developed requirements for a project containing sensitive information. The requirements were approved, and the solution was implemented. What should the BA do to ensure these requirements are maintained for future reference?

Options:
A.

Store the requirements package on a secure shared drive.

B.

Send the requirements package to stakeholders in a password-protected email.

C.

Print the requirements package and distribute it to stakeholders in person.

D.

Archive the requirements package in the business analysis portal.