What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)

Options:
A.

There is no such thing as Sprint 0.

B.

Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.

C.

Make the complete project plan to commit date, budget, and scope to the stakeholders.

D.

Determine the composition of the Development Teams so they have the capacity to deliver the completed

forecast.

E.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

Scrum PSM-I Premium Access
Questions 32

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

Options:
A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, reporting to a chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Questions 33

A Scrum Team is a cohesive unit of professionals that consists of which of the following? (Choose all that

apply.)

Options:
A.

Users.

B.

One Scrum Master.

C.

Developers.

D.

Customers.

E.

One Product Owner.

Questions 34

The Product Backlog is ordered by:

Options:
A.

The Product Owner with the most valuable items placed at the top.

B.

Risk, where safer items are at the top, and riskier items are at the bottom.

C.

Items are randomly arranged.

D.

Size, where small items ale at the top and large items are at the bottom.

Questions 35

One of the Scrum events is the Daily Scrum. What are two intended outcomes ot the Daily

Scrum?

(choose the best two answers)

Options:
A.

An updated Scrum board to make Sprint progress transparent for the

stakeholders

B.

Identification of impediments that may prevent the Developers from achieving

the Sprint Goal.

C.

A status report tor the upper management indicating what each individual has

done, will be doing, and what is impeding him/her.

D.

A shared understanding ot the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

An update of completed tasks and ot the remaining work so the Scrum Master

can plan the next day.

Questions 36

Who must attend the Daily Scrum?

Options:
A.

The Scrum Master and Product Owner.

B.

The Development Team.

C.

The Development Team and Product Owner.

D.

The Scrum Team.

E.

The Development Team and Scrum Master.

Questions 37

Select two ways in which technical debt impacts transparency. (Choose two.)

Options:
A.

When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.

B.

It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.

C.

As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.

D.

It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.

Questions 38

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

Options:
A.

True

B.

False

Questions 39

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)

Options:
A.

Consulting with the Development Team.

B.

Prioritizing the list and working on them in order.

C.

Arranging a triage meeting with all project managers.

D.

Alerting management to the impediments and their impact.

Questions 40

As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

Options:
A.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

B.

Find another Scrum Team to give the excess work to.

C.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

D.

Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.