Which statement best describes a Product Owner’s responsibility?

Options:
A.

Optimizing the value of the work the Development Team does.

B.

Managing the project and ensuring that the work meets the commitments to the stakeholders.

C.

Directing the Development Team.

D.

Keep stakeholders from distracting the Development Team.

Scrum PSM-I Premium Access
Questions 122

What are three ways Scrum promotes self-organization? (Choose three.)

Options:
A.

By not allowing documentation.

B.

By the Development Team deciding what work to do in a Sprint.

C.

By preventing stakeholders from entering the development room.

D.

By removing titles for Development Team members.

E.

By being a lightweight framework.

Questions 123

Which are characteristics of the Daily Scrum?

(choose the best two answers)

Options:
A.

Its location and time remain constant

B.

Its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint

Backlog.

C.

It is tree form and designed to promote conversatiom

D.

It is facilitated by the team lead.

E.

It is held first thing in the morning.

F.

It consists of the Scrum Master asking the team tor status.

Questions 124

Which of the following is an accountability of a Tester on a Scrum Team?

(choose the best answer)

Options:
A.

Executing tests, finding defects, and reporting them to the Developers.

B.

Refreshing and communicating the Definition of Done to the Product Owner.

C.

Scrum has no Tester accountability. The Developers are accountable for quality.

D.

Verifying the work of the Developers.

E.

Tracking defect rates to ensure they improve each Sprint.

Questions 125

Every Scrum Team should nave:

(choose the best answer)

Options:
A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint

C.

At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.

Questions 126

The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

Options:
A.

Add the item to the top of the Product Backlog.

B.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

C.

Add the item to the Sprint Backlog for the next Sprint.

D.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

E.

Add the item to the current Sprint and drop an item of equal size.

Questions 127

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

Options:
A.

Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.

B.

Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.

C.

Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.

D.

Present the Product Owner with an ordered Product Backlog to use.

E.

Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.

Questions 128

Every Scrum team must have a Product Owner and Scrum Master.

Options:
A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a business analyst in the Development Team.

C.

False. A Scrum Master is only required when asked for by the Development Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Questions 129

What does it mean for a Development Team to be cross-functional?

Options:
A.

The Development Team includes not only developers but also business analysts, architects, and testers.

B.

The Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software.

C.

Developers on the Development Team work closely with business analysts, architects, developers and testers who are not on the team.

D.

The Development Team is a virtual team drawing from separate teams of business analysts, architects, developers and testers.

Questions 130

Which of the following is required by Scrum? (Choose all that apply.)

Options:
A.

Sprint Retrospective.

B.

Members must be stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release planning.

E.

All of the above.