Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free Scrum PSM-II Practice Exam with Questions & Answers

Questions 1

Which statements are true about the Sprint Goal?

(choose the best two answers)

Options:
A.

Sprint Goals often change during the Sprint as new insights emerge during the work.

B.

During Sprint Planning, the Scrum Team crafts a Sprint Goal based on anobjective that the Product Owner would like to achieve that Sprint.

C.

Sprint Goals give Developers flexibility and creativity on how to implement functionality during the Sprint

D.

The use of Sprint Goals is optional in the Scrum Framework

Scrum PSM-II Premium Access
Questions 2

Towards the end of Sprint Planning, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make it clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?

(choose the best two answers)

Options:
A.

They discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

B.

The team splits up and everybody takes as much time as they need to study the Product Backlog items first. The Product Owner should be available to answer individual questions. The group reconvenes when all team members are better prepared and restart the Sprint Planning meeting before the Sprint can start.

C.

If all agree, they can continue the Sprint Planning meeting as a team past its timebox, until an adequate number of Product Backlog items are well enoughunderstood for the Developers to make a complete forecast. Then start the Sprint.

D.

The Developers forecast the most likely Product Backlog items to meet the business objective and create a Sprint Backlog based on a likely initial design and plan. Once the timebox for the Sprint Planning event is over, they start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

Questions 3

An important aspect of Scrum are timeboxes. Select two ways in which timeboxing reinforces the creation of value.

(choose the best two answers)

Options:
A.

Timeboxing assures that a Product Owner does not interrupt the Developers during a Sprint.

B.

Scrum Teams can determine on their own how much overtime is acceptable for a timebox- generally expressed as a percentage of the timebox.

C.

Timeboxes encourage the people who are closest to the problem to create the best possible result in the time allotted, given the current context.

D.

Timeboxes help everyone focus on the same problem at the same time.

Questions 4

Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are primarily working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.

Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.

What might explain why this Scrum Team is struggling to craft a Sprint Goal?

(choose all that apply)

Options:
A.

Scrum might not be the best framework for the work done by this team.

B.

The Sprints are too long.

C.

The Product Owner does not have the mandate to make decisions about items on the Product Backlog nor their ordering.

D.

The Product Owner is not communicating the Product Goal that they want to achieve in upcoming Sprints.

E.

The Scrum Team is too big.

Questions 5

Self-management is more effective when it happens within boundaries.

Select two relevant boundaries for self-management provided by the Scrum framework.

(choose the best two answers)

Options:
A.

Timeboxing work to allow for frequent inspection.

B.

Clearly defining sub-responsibilities and handovers within the Scrum Team.

C.

Creating a valuable and useful Increment by the end of each Sprint.

D.

Having an even number of members in a Scrum Team to be able to do pair programming and be more productive.

Questions 6

A Scrum Team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?

(choose the best answer)

Options:
A.

Coach the Product Owner and the Developers on the purpose of Scrum events and let them figure out how to deal with this situation.

B.

Start attending the Daily Scrum so that whenever the Developers have a conflict with

the Product Owner, the Scrum Master can resolve the conflict

C.

Nothing. The Product Owner can continue to track progress at the Daily Scrum.

D.

Ask the Product Owner to stop attending the Daily Scrum.

Questions 7

How should requirements be distributed when multiple Scrum Teams work on the same product?

(choose the best answer)

Options:
A.

They must be selected from one Product Backlog in such a way that each Scrum

Team has an equal volume of requirements per Sprint.

B.

The Scrum Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.

C.

The Scrum Team with the highest velocity pulls items from an overall Product

Backlog first

D.

The Product Owner decides by providing each team with its own Product Backlog.

Questions 8

Eight months ago your company started developing a new product consisting ot several major components. You are the Scrum Master on the team building the "core" component of the product; your component also integrates all the othercomponents.

The Scrum Teams work in monthly Sprints, and the team has forecast that it will deliver the integrated product in three Sprints. Recently the team's progress slowed because of changes to the other components that they integrate. The program manager is extremely upset when they find out that the team will need two more Sprints. The project managers of the other components confirm their adherence to the original forecast.

As a Scrum Master, what could you do to help the Product Owner?

(choose the best answer)

Options:
A.

You calculate how many additional developers it would take to increase velocity to make the original date. You inform the program manager of the additional budget for these developers. This would then allow meeting the original forecast

B.

You remove all items from the Product Backlog tor which development is forecast to be beyond the expected date.

C.

You suggest working with the program manager and the project managers of the

other components on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.

D.

You lengthen your Sprints to accommodate the delays.

Questions 9

Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?

(choose the best three answers)

Options:
A.

It serves to track the percent completeness of a Product Backlog item during the Sprint.

B.

During the Sprint it helps the Developers identify the work remaining for an

Increment to be ready for release by the end of a Sprint.

C.

It creates transparency into the state of the Increment when it is inspected at the Sprint Review.

D.

It guides the Developers when creating a forecast at the Sprint Planning.

E.

It provides a template for the documentation of the product Increment.

F.

It is a checklist to inspect whether the Developers have performed their tasks by the end of a Sprint.

Questions 10

The relationship between the Product Owner and the Developers has degraded over time.

The Developers are growing increasingly angry with the Product Owner for changing the requirements all the time and not being available enough. The Product Owner is angry with the Developers for changing requirements during implementation. What guidance should the Scrum Master offer?

(choose the best answer)

Options:
A.

Take everyone to a 2-day off-site event to relax and re-align. It is liberating to take people's minds away from work.

B.

Ask each person's functional manager to instruct their employees that they must collaborate better, or be removed from the team.

C.

Address why requirements change during the Sprint Retrospective. Ask the

Developers and the Product Owner to talk about why the requirements are changing

and consider the impact on value during this discussion.

D.

Ask for a project manager or other external resource to mediate and temporarily take over for the Product Owner.