Free Scrum PSM-I Practice Exam with Questions & Answers | Set: 3

Questions 21

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

Options:
A.

True

B.

False

Scrum PSM-I Premium Access
Questions 22

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

Options:
A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Development Team's plan for the Sprint.

E.

It is ordered by the Product Owner.

Questions 23

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Options:
A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Questions 24

What is the recommended size for a Scrum Team? (Choose the best answer.)

Options:
A.

At least 7.

B.

9

C.

10 or fewer.

D.

7 plus or minus 3.

Questions 25

Why does the Product Owner want the Development Team to adhere to its definition of “Done”?

Options:
A.

To have complete transparency into what has been done at the end of each Sprint.

B.

To be able to reprimand the team when they don’t meet their velocity goal for the Sprint.

C.

To know what the team will deliver over the next three Sprints.

D.

To predict the team’s productivity over time.

Questions 26

The Development Team should have all the skills needed to:

Options:
A.

Turn Product Backlog items into an Increment of potentially releasable product functionality.

B.

Do all of the development work, except for specialized testing that requires additional tools and environments.

C.

Complete the project within the date and cost as calculated by the Product Owner.

Questions 27

What are two ways that regulatory compliance issues are dealt with in Scrum?

(choose the best two answers)

Options:
A.

They are addressed by a separate team who is responsible for compliance

issues.

B.

They are addressed along with functional development of the product.

C.

They are discussed, determined, and documented before the actual feature

development Sprints.

D.

They are added to the Product Backlog and addressed in early Sprints, while

always requiring at least some business functionality, no matter how small.

Questions 28

What is the time-box for the Sprint Planning meeting?

Options:
A.

4 Hours for a monthly Sprint.

B.

8 Hours for a monthly Sprint.

C.

Monthly.

D.

Whenever it is done.

Questions 29

Who should know the most about the progress toward a business objective or a release?

Options:
A.

The Project Manager.

B.

The Scrum Master.

C.

The Development Team.

D.

The Product Owner.

Questions 30

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

Options:
A.

The Scrum Team with the highest velocity pulls Product Backlog items first.

B.

The Development Teams pull in work in agreement with the Product Owner.

C.

The Product Owner should provide each team with its own Product Backlog.

D.

Each Scrum Team takes an equal numbers of items.

E.

The Product Owner decides.