Who owns the Sprint Backlog?

Options:
A.

The Scrum Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

Scrum PSM-I Premium Access
Questions 22

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Options:
A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Questions 23

What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)

Options:
A.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

B.

Add security concerns to the definition of “Done”.

C.

Add a Sprint to specifically resolve all security concerns.

D.

Delegate the work to the concerned department.

E.

Have the Scrum Team create Product Backlog items for each concern.

Questions 24

What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)

Options:
A.

Put them on a separate list on the Scrum board, available for all to see.

B.

Add them to the Product Backlog and keep the Product Owner posted on the expected effort.

C.

Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.

D.

Add them to the definition of “Done” so the work is taken care of every Sprint.

Questions 25

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

Options:
A.

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Questions 26

What is the recommended size for a Development Team?

Options:
A.

7 plus or minus 3.

B.

At least 7.

C.

9.

D.

3 to 9.

Questions 27

When does a Sprint conclude?

(choose the best answer)

Options:
A.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

B.

When the Sprint Retrospective is complete.

C.

When all the tasks are completed by the Developers.

D.

When all Product Backlog items meet their Definition of Done.

Questions 28

How is management external to the Scrum Team involved in the Daily Scrum? (Choose the best answer.)

Options:
A.

The Scrum Master speaks on their behalf.

B.

Managers are not required at the Daily Scrum.

C.

Management gives an update at the start of each Daily Scrum.

D.

The Product Owner represents their opinions.

Questions 29

(What are two ways that regulatory compliance requirements are dealt with in Scrum?

Choose the best two answers.)

Options:
A.

They are addressed by a separate team who is responsible for compliance issues.

B.

They are discussed, analyzed, and documented before the first Sprint can begin.

C.

They are added to the Product Backlog and addressed during each Sprint, alongside the creation of new Product capabilities.

D.

They are addressed as part of meeting the Definition of Done during each Sprint.

Questions 30

Which statement best describes Scrum?

(choose the best answer)

Options:
A.

A defined and predictive process that conforms to the principles of Scientific

Management

B.

A framework to generate value through adaptive solutions tor complex problems.

C.

A cookbook that defines best practices tor software development.

D.

A complete methodology that defines how to develop software.