Free Scrum PSM-I Practice Exam with Questions & Answers

Questions 1

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

Options:
A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Scrum PSM-I Premium Access
Questions 2

Which two ways of creating Scrum Teams are consistent with Scrum's values?

(choose the best two answers)

Options:
A.

Bring all the people together and let them organize into Scrum Teams

B.

Managers personally re-assign current subordinates to new teams.

C.

Existing teams propose how they would like to go about organizing into the new

structure.

D.

Managers collaborate to assign individuals to specific teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Questions 3

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

Options:
A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

Questions 4

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

Options:
A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Questions 5

When a Development Team is having trouble delivering a working Increment because they don’t understand a functional requirement, what should they do?

Options:
A.

Add a specialist to the Development Team.

B.

Partially complete the functionality, and discuss the remaining work at the Sprint Review.

C.

Collaborate with the Product Owner to determine what is possible and acceptable.

D.

Defer the work to a more appropriate Sprint.

Questions 6

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

Options:
A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Questions 7

Who should make sure everyone on the Development Team does their tasks for the Sprint?

Options:
A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

E.

All of the above.

Questions 8

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

Options:
A.

By ensuring the meetings start and end at the proper time.

B.

By removing impediments that hinder the Development Team.

C.

By facilitating Development Team decisions.

D.

By keeping high value features high in the Product Backlog.

Questions 9

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

Options:
A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Questions 10

What two factors are best considered when establishing the Sprint length? (Choose two.)

Options:
A.

The organization has mandated similar length sprints.

B.

The level of uncertainty over the technology to be used.

C.

The frequency at which team formation can be changed.

D.

The risk of being disconnected from the stakeholders.