Weekend Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Master the Project Management Professional (2024 Version) PMP Exam with Confidence!

Questions 401

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change

in project scope.

How should the project manager respond to this requirement?

Options:

A.

Proceed with the existing company governance policy.

B.

Perform an analysis to assess the impact on the project.

C.

Directly comply with the financial regulations.

D.

Escalate the issue to upper management and let them decide.

Buy Now
Questions 402

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

Options:

A.

Submit a change request and allocate the budget and resources needed for execution.

B.

Confirm that the budget and resources are available to execute the work request.

C.

Check the alternative resources available in the organization for the request.

D.

Evaluate the nature of the request and plan communication accordingly.

Buy Now
Questions 403

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

Options:

A.

Risk to delivery

B.

Technical complexity

C.

Business value

D.

Estimation accuracy

Buy Now
Questions 404

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

Options:

A.

Review the Pareto diagram to identify the source of delays.

B.

Meet with the team in 2 weeks to respond to all of the open tasks.

C.

Consolidate the decision-making authority to remain with the project manager.

D.

Delegate the decision-making authority of some tasks to the team.

Buy Now
Questions 405

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the

importance of this document to the project manager?

Options:

A.

Needed to close the work breakdown structure (WBS).

B.

Needed to share it with the stakeholders.

C.

Needed to close out the project or a phase.

D.

Needed to release the team at the end of the project.

Buy Now
Questions 406

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.

What should the project manager do next?

Options:

A.

Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.

B.

Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.

C.

Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.

D.

Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.

Buy Now
Questions 407

After a recent status review meeting, the project manager becomes aware that an influential stakeholder is unclear about the purpose and benefits of the project Consequently, the stakeholder has questioned the viability of continuing the project What should the project manager do next to address the situation?

Options:

A.

Speak with the project sponsor to find out if the stakeholder would agree to a one-on-one review session

B.

Log the stakeholder's comments in the risk register as a high-impact threat to the project's completion

C.

Consider the stakeholder's concerns and review the project charter with the project sponsor.

D.

Note the stakeholder's concerns but disregard them with regard to the project activities.

Buy Now
Questions 408

A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.

Which measure should mitigate the impact of this key resource's departure?

Options:

A.

Offer a new contract to the resource who is leaving.

B.

Establish a proactive knowledge-sharing plan.

C.

Update the risk register and inform the customer.

D.

Develop a contingency budget to replace the key resource.

Buy Now
Questions 409

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

Options:

A.

Evaluate the cost of the additional requested work.

B.

Evaluate the impact and submit a change request.

C.

Discuss the requested change with the sponsor.

D.

Discuss the requested change with the team.

Buy Now
Questions 410

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

Options:

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Buy Now
Questions 411

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Buy Now
Questions 412

A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be

engaged in how the project will be executed.

How should the project manager proceed?

Options:

A.

Create an environment where the agreement is reached by a majority vote.

B.

Create an environment where the agreement is reached through discussion.

C.

Establish recurring brainstorming sessions to discuss project issues.

D.

Allow team members to contribute ideas in a stream-of-consciousness mode.

Buy Now
Questions 413

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

Options:

A.

Modify the PMO template to include the information.

B.

Contact the senior manager and discuss their needs.

C.

Give the senior manager access to the product backlog.

D.

Organize a review of the kanban board with the manager.

Buy Now
Questions 414

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.

Assign the task to someone else on the team.

B.

Discuss it with the team member in confidence.

C.

Discuss this matter during the project meeting.

D.

Include this item in the risk register.

Buy Now
Questions 415

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

Options:

A.

Interview the most resistant team members to persuade them to try to accept an agile approach.

B.

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

C.

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

D.

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.

E.

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

Buy Now
Questions 416

A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.

What should the project manager do?

Options:

A.

Use the compliance issues to identify coaching and mentoring opportunities.

B.

Log the feedback from the compliance gaps in the lessons learned register.

C.

Review this with the project sponsor to avoid compliance gaps and issues.

D.

Discuss the suggestions with the staff responsible for the compliance issues.

Buy Now
Questions 417

A project manager is assigned to deliver a development project with subcontracted resources from a sister company. What should the project manager do to ensure a smooth inclusion of the new subcontracted resources?

Options:

A.

Organize a team-bonding exercise with the subcontractors.

B.

Facilitate a working session to review the ground rules.

C.

Share the project team ground rules with the subcontractors.

D.

Schedule a formal meeting to cover the mission and vision.

Buy Now
Questions 418

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

Options:

A.

Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done. shared.

B.

Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.

C.

Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.

D.

Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.

Buy Now
Questions 419

A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?

Options:

A.

Discuss ground rules with the team that will include daily meetings.

B.

Use one-to-one virtual meetings because they are more efficient.

C.

Ask senior management for coaching regarding this situation.

D.

Agree on a new time and reschedule the daily standups.

Buy Now
Questions 420

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

Options:

A.

Solution architecture

B.

Product backlog

C.

Statement of work (SOW)

D.

Business case

Buy Now
Questions 421

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

Options:

A.

Ask the new team member to focus only on development and not do the testing.

B.

Coach the new team member to conduct the testing the way it has always been done for this project.

C.

Schedule a meeting with the new team member to learn about the new method of testing.

D.

Request that the new team member do the testing the way it has always been done for this project.

Buy Now
Questions 422

A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?

Options:

A.

Find available professionals within the organization to fill the gaps.

B.

Allocate funding for seeking external professionals to fill the gaps.

C.

Determine the possibility for team members to split up the required tasks.

D.

Request additional budget for team training for the missing expertise.

Buy Now
Questions 423

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager

do to get this information?

Options:

A.

Organize a one-on-one conversation with each stakeholder.

B.

Request stakeholders articulate their motivations at the kick-off meeting.

C.

Email project objectives to all stakeholders and ask for endorsement.

D.

Identify each stakeholder's motivations from the business case.

Buy Now
Questions 424

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

Options:

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Buy Now
Questions 425

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

Options:

A.

Send evidence to the new stakeholder that the project's status was sent according to the schedule

B.

Suggest that the new stakeholder review the project status before the next board meeting

C.

Share the communications management plan with the new stakeholder

D.

Discuss project requirements with the new stakeholder, and update the communications management plan.

Buy Now
Questions 426

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?

Options:

A.

Schedule a meeting with the project team to reinforce the ground rules.

B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action

C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.

D.

Ask the functional manager to replace team members not following the ground rules

Buy Now
Questions 427

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

Options:

A.

Retrospect frequently and suggest improvements.

B.

Incorporate a predictive approach for this element.

C.

Implement mitigation strategies for this element

D.

Request additional team members to help with improvements

Buy Now
Questions 428

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

PMP Question 428

Options:

Buy Now
Questions 429

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Buy Now
Questions 430

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

Options:

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Buy Now
Questions 431

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

Options:

A.

Coach those team members lacking hybrid knowledge to learn on the job.

B.

Change the team to include hybrid experts

C.

Assess the required training per team member.

D.

Deliver hybrid training to all team members

Buy Now
Questions 432

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

Options:

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

Buy Now
Questions 433

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.

What should the project manager do?

Options:

A.

Prepare and submit a status report to the steering committee to update performance monitoring

B.

Determine the data to be monitored during the project as well as the expected performance and targets.

C.

Update the communications management plan to consider performance review meetings with the project stakeholders

D.

Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project

Buy Now
Questions 434

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

Options:

A.

Escalate to the management team to increase the timeline based on the complexity of the project

B.

Wait for the other project estimates before planning the schedule

C.

Prioritize and estimate the milestones for the high-level requirements based on historical data

D.

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan

Buy Now
Questions 435

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed

Which two actions should the project manager take? (Choose two)

Options:

A.

Convince the customer to leave the second milestone in place and not change it.

B.

Escalate the issue to upper management to resolve the problem and suggest a plan.

C.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

D.

Ask the customer for their priorities regarding the requirements for the second milestone

E.

Tell the customer that moving the milestone has a very high impact on the cost of the project

Buy Now
Questions 436

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

Options:

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Buy Now
Questions 437

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Buy Now
Questions 438

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all defects identified during testing were resolved before implementation

B.

Ensured that all of the required tasks identified in the scope were completed successfully

C.

Ensured that all documentation was completed post implementation before closing the project

D.

Ensured that all the required approvals were received per the organizational procedures

Buy Now
Questions 439

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.

Have the team inform senior management of the situation and ask for recommendations.

D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Buy Now
Questions 440

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?

Options:

A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase

B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

C.

Consult with experts on methods to reduce costs and increase the financial value of the project

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner

Buy Now
Questions 441

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

Options:

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Buy Now
Questions 442

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Buy Now
Questions 443

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

Options:

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

Buy Now
Questions 444

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?

Options:

A.

Wait for the requirements to be more clear before any further action is taken on the project

B.

Ignore the unclear requirements and focus on the delivery plan of the project

C.

Escalate the issue of unclear requirements to the management team and wait for final authorization

D.

Break down the requirements and prioritize the requirements into iterative work packages

Buy Now
Questions 445

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Buy Now
Questions 446

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Buy Now
Questions 447

A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

PMP Question 447

Options:

Buy Now
Questions 448

A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.

What can the project manager do to help increase the team's motivation and engagement with the project?

Options:

A.

Review sprint progress with the project team members

B.

Set up one-on-one meetings with the project team members

C.

Review sprint planning procedures with the project team members

D.

Perform a sprint retrospective with the project team members

Buy Now
Questions 449

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

Options:

A.

Review the project scope and negotiate with the contractor

B.

Refuse the offer as it is included in the initial project scope

C.

Review the project costs and communicate this to the project sponsor

D.

Submit a change request to approve the offer

Buy Now
Questions 450

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

Options:

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2024 Version)
Last Update: May 12, 2024
Questions: 1702

PDF + Testing Engine

$599
$209.65

Testing Engine

$449
$157.15

PDF (Q&A)

$399
$139.65