A project manager is assigned to oversee the deployment of a new product that

will be used by the entire organization. A key success factor for the project is the timely

and successful adoption of the new solution by all entities.

What should the project manager do to ensure the success of this critical project?

Options:

A.

Considering the project scope and the multiple entities impacted by the solution,

communicate with the stakeholders and ask them to adhere to the date.

B.

Ask the project sponsor to issue a directive requesting all business entities to

accept the date set for the new solution launch.

C.

Given the size of the organization and the multiple parties involved, discuss the

launch date with the CEO and then communicate it to all entities.

D.

Engage in creative and iterative negotiations with the leaders of each entity to

agree on the launch date.

Buy Now
Questions 2

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

Buy Now
Questions 3

A project sponsor receives project information and updates in a timely manner, but

the sponsor is concerned because key information is missing in the reports. What should the

project manager do?

Options:

A.

Review the communication needs of key stakeholders.

B.

Confirm that the project information is understood and feedback is received.

C.

Determine communication methods, frequency, and level of detail.

D.

Provide all project information to the stakeholder.

Buy Now
Questions 4

A local company is developing a new product and. for the first time, using a remote team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Buy Now
Questions 5

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

Options:

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

Buy Now
Questions 6

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

PMP Question 6

Options:

Buy Now
Questions 7

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Buy Now
Questions 8

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team.to accelerate the iterations and avoid interruptions.

B.

Discuss the problem with the team and decide how to do the work together.

C.

Verify team performance and ask for improvement during daily standup meetings.

D.

Recommend that the project sponsor increases the budget to bring new resources.

Buy Now
Questions 9

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Buy Now
Questions 10

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

Options:

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Buy Now
Questions 11

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

Options:

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Buy Now
Questions 12

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets withthe stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Buy Now
Questions 13

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

Options:

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Buy Now
Questions 14

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

Options:

A.

Sprint plans

B.

Retrospective results

C.

Sprint report

D.

Project status report

Buy Now
Questions 15

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

Options:

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

Buy Now
Questions 16

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

Options:

A.

Update the restriction log with the new team capacity.

B.

Explain the new project requirements to the team.

C.

Update the project budget with the released team members.

D.

Explain the new team velocity to the customer.

Buy Now
Questions 17

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

Options:

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Buy Now
Questions 18

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

Options:

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

Buy Now
Questions 19

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

Options:

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

Buy Now
Questions 20

A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?

Options:

A.

Release plan Sy

B.

Product roadmap

C.

Kanban board

D.

Burndown chart

Buy Now
Questions 21

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

Options:

A.

Include the requirement into the project and schedule it as soon as possible

B.

Inform the project sponsor about the situation and request assistance

C.

Evaluate the impact that the inclusion of this new requirement will have on project performance

D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope

Buy Now
Questions 22

A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.

What should the project manager do next?

Options:

A.

Extend the sprint timeline so the learn can work on the missing feature.

B.

Inform the product owner that this issue needs to be escalated to the executive level.

C.

Collaborate with the product owner and the team to plan the following sprint

D.

Initiate the change request process to include these missing features.

Buy Now
Questions 23

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Buy Now
Questions 24

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

Options:

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Buy Now
Questions 25

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

Options:

A.

Distributed a detailed quality management plan to the key stakeholders.

B.

Included the final report during the closing phase to ensure common understanding.

C.

Identified key stakeholders and included all of them in project agreement discussions.

D.

Performed project reporting according to the communications management plan.

Buy Now
Questions 26

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

Options:

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

Buy Now
Questions 27

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.

Ensure that the requirements for the project are understood and that the objectives

are verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannot

be any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in the

agreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Buy Now
Questions 28

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

Options:

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Buy Now
Questions 29

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.

What should the project manager do first?

Options:

A.

Review the benefits of the proposed changes in relation to the business case.

B.

Assess the time overrun, and start implementation to avoid additional delays.

C.

Request a provisional budget increase to avoid any budget overruns.

D.

Motivate the team to avoid the frustration of working on a prolonged project.

Buy Now
Questions 30

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Buy Now
Questions 31

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

Options:

A.

Consult the project sponsor and request their feedback

B.

Consult the product owner and request a complete prioritization session

C.

Consult a senior project manager within the organization and request their expert judgement

D.

Consult a senior developer within the organization and request their input.

Buy Now
Questions 32

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

Options:

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

Buy Now
Questions 33

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Buy Now
Questions 34

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

Options:

A.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.

B.

Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.

C.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).

D.

Inform the scrum master so that the change can be discussed directly with the stakeholder.

Buy Now
Questions 35

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Options:

Buy Now
Questions 36

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.

Buy Now
Questions 37

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

Options:

A.

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.

B.

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.

C.

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.

D.

Secure some additional funding to recruit more resources to the project team to enable faster delivery.

Buy Now
Questions 38

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

Options:

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

Buy Now
Questions 39

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?

Options:

A.

Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

B.

Provide an incentive plan so the team members will work more unaccounted hours on multiple projects

C.

Brainstorm with the team members on how they can deliver on multiple projects within the given budget

D.

Instruct the team members to spread evenly across projects so mistakes will not occur within the current budget.

Buy Now
Questions 40

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Options:

Buy Now
Questions 41

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

Options:

A.

Prioritize project A over project B since A is an external project and B is an internal project.

B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.

C.

Engage the human resource manager to employ a machine learning expert for project A.

D.

Plan project A to start at the end of project B when the machine learning expert is available.

Buy Now
Questions 42

A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for oneof the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, theproject manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part oftheir deliverable.

What should the project manager do?

Options:

A.

Add the feature to the supplier's requirement list so they can deliver it.

B.

Ask the supplier to accommodate the additional scope under the current agreement.

C.

Ensure the project team understands the agreement and contract in place with the supplier.

D.

Monitor the work the business analyst is performing to avoid scope creep.

Buy Now
Questions 43

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

Options:

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Buy Now
Questions 44

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Buy Now
Questions 45

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Questions 46

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.

Work with the finance team to transition to incremental budgeting.

B.

Request the finance team to allocate a budget based on historical data.

C.

Provide the budget to the finance team for only the planned increments.

D.

Extrapolate the budget based on the current cost performance index (CPI).

Buy Now
Questions 47

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?

Options:

A.

Provide opportunity for team members to learn and adjust to the technology.

B.

Move team members who are not performing from the team.

C.

Add new members to the team and increase the velocity

D.

Re-assign the project to a team that has worked with this technology

Buy Now
Questions 48

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

Buy Now
Questions 49

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

Buy Now
Questions 50

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2024 Version)
Last Update: Dec 4, 2024
Questions: 1702

PDF + Testing Engine

$599
$239.6

Testing Engine

$449
$179.6

PDF (Q&A)

$399
$159.6