In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Options:
A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

AACE International PSP Premium Access
Questions 52

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Options:
A.

8 days

B.

6 days

C.

4 days

D.

5 days

Questions 53

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:
A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Questions 54

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

Options:
A.

Budget at completion (BAC)

B.

Budgeted cost of work performed (BCWP)

C.

Estimate to complete (ETC)

D.

Estimate at completion (EAC)

Questions 55

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

Options:
A.

Labor hours or dollars.

B.

Direct or indirect cost.

C.

Earned or budgeted cost yearly.

D.

Linear feet or dollars.

Questions 56

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:
A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Questions 57

A driving relationship is _____________________.

Options:
A.

A critical relationship.

B.

A finish-to-start relationship.

C.

The link between two related activities.

D.

The link between a predecessor and the activity whose dates it controls.

Questions 58

The EBS is established by:

Options:
A.

The contractor s planning and scheduling office

B.

The government entity with the authority to approve/stop the work

C.

The entity with the authority to fund and direct the enterprise

D.

The contractors and subcontractors

Questions 59

Identify the late finish to develop plans and specs.

PSP Question 59

Options:
A.

9 months.

B.

10 months.

C.

8 months.

D.

7 months.

Questions 60

Determine the correct formula and date for the late start for Activity 9001.

PSP Question 60

Options:
A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 -> 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 -> 11-20-02.

Exam Code: PSP
Certification Provider: AACE International
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Oct 5, 2025
Questions: 216

AACE International Related Exams

AACE International Free Exams

AACE International Free Exams
Unlock free AACE International exam resources and practice tests at Examstrack. Boost your AACE International exam readiness with top-notch materials.