Weekend Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Free AACE International PSP Practice Exam with Questions & Answers | Set: 5

Questions 41

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

PSP Question 41

Options:
A.

2 cranes

B.

1 crane

C.

4 cranes

D.

3 cranes

Questions 42

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:
A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Questions 43

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

PSP Question 43

Options:
A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Questions 44

Determine the driving activity for Activity 10001.

PSP Question 44

Options:
A.

Activity 11001.

B.

Activity 10002.

C.

Activity 9005.

D.

There is no driving activity for Activity 10001 in the backward pass.

Questions 45

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

PSP Question 45

Options:
A.

407 days

B.

362 days

C.

255 days

D.

267 days

Questions 46

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

Options:
A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

Questions 47

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

Options:
A.

Delay due to SDOT's other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Questions 48

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

Options:
A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Exam Code: PSP
Certification Provider: AACE International
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Jul 12, 2025
Questions: 163

AACE International Related Exams

AACE International Free Exams

AACE International Free Exams
Unlock free AACE International exam resources and practice tests at Examstrack. Boost your AACE International exam readiness with top-notch materials.