When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Total float is defined as the amount of time an activity can be delayed without impacting
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
Project delays are best analyzed
What does the heavy, vertical line at "X" represent?
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:
The addition of which of the following relationships would cause a logic loop?
Determine the correct formula and date for the late finish for Activity 6002.