Determine the correct formula and date for the late finish for Activity 6002.

Options:
A.

LS of 6003 plus 1 day equaling 09 Mar 2023

B.

LS of 6003 less 1 day equaling 09 Mar 2022

C.

LS of 6003 less 1 day equaling 09 Mar 2023

D.

LS of 6003 plus 1 day equaling 09 Mar 2022

AACE International PSP Premium Access
Questions 12

What is the remaining work duration of Active D?

PSP Question 12

Options:
A.

4.

B.

11

C.

8.

D.

3.

Questions 13

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

PSP Question 13

Options:
A.

91 days

B.

183 days

C.

145 days

D.

53 days

Questions 14

How many work days does it take to move the product from testing to sale?

PSP Question 14

Options:
A.

60.

B.

70.

C.

100.

D.

90.

Questions 15

Determine the correct formula and date for the late finish for Activity 2002.

PSP Question 15

Options:
A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Questions 16

Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?

Options:
A.

All managers should be encouraged to review contiguous activity status

B.

The process of each activity should be indicated by the responsible manager

C.

The critical path should not be revisited to ensure all the downstream logic and durations are still accurate

D.

The project team should be asked to review status for accuracy

Questions 17

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

Options:
A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects

Questions 18

Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

PSP Question 18

Options:
A.

12-27-03 and 24 days of float

B.

12-18-03 and 4 days of float

C.

12-17-03 and 4 days of float

D.

12-18-03 and 25 days of float

Questions 19

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

Options:
A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

Questions 20

What activities are concurrent to Activity 2001 in the "normal" schedule?

PSP Question 20

Options:
A.

7001.

B.

1001.

C.

1000.

D.

2003.

Exam Code: PSP
Certification Provider: AACE International
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Oct 30, 2025