Free AACE International PSP Practice Exam with Questions & Answers | Set: 3

Questions 21

Project delays are best analyzed

Options:
A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

AACE International PSP Premium Access
Questions 22

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

Options:
A.

Delay due to SDOT's other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Questions 23

What is the result of a forward pass calculation?

Options:
A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Questions 24

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

Options:
A.

The duration for drywall installation should De proportional to how critical the activity is

B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration

C.

Review the location of drywall work in the contract drawings

D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work

Questions 25

When resource leveling craft labor for a critical path schedule, the scheduler

Options:
A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

Questions 26

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

Options:
A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Questions 27

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

PSP Question 27

Options:
A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Questions 28

What day would Activity C complete if the duration of Activity B was reduced to zero?

Options:
A.

50

B.

20

C.

30

D.

40

Questions 29

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:
A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

Questions 30

How much Total Float does drafting the product manual have?

PSP Question 30

Options:
A.

15 workdays.

B.

0 workdays.

C.

10 workdays.

D.

5 workdays.

Exam Code: PSP
Certification Provider: AACE International
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Oct 30, 2025
Questions: 216

AACE International Related Exams

AACE International Free Exams

AACE International Free Exams
Unlock free AACE International exam resources and practice tests at Examstrack. Boost your AACE International exam readiness with top-notch materials.