If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?

Options:
A.

Predecessor is Activity 4001. successor is Activity 9004

B.

Predecessor is Activity 8001, successor is Activity 5001

C.

Predecessor is Activity 5001, successor is Activity 8001

D.

Predecessor is Activity 4001, successor is Activity 9003

AACE International PSP Premium Access
Questions 32

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

PSP Question 32

Options:
A.

2.

B.

1.

C.

Does not change.

D.

3.

Questions 33

NO: 98

The activity with the most total float is:

PSP Question 33

Options:
A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

Questions 34

Which of the following is not an internal stakeholder?

Options:
A.

Owner

B.

installer

C.

Subcontractor

D.

Prime Contractor

Questions 35

What is accurate about Activity 7001 in the precedence diagram?

Options:
A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Questions 36

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

Options:
A.

Proceed with company processes even if they conflict with the client

B.

The client contract specifications always have priority

C.

Review any differences and negotiate workable specifications

D.

Suggest that the client issue a change order, accepting the contractor's processes

Questions 37

Prior to the start of work, Management determined the need to make the Product available 10 workdays earlier than planned. Which activities need to be expedited?

Options:
A.

Product Testing. Manufacture Product and Package Product

B.

Product Testing and Manufacture Product

C.

Draft Product Manual. Proof Product Manual, and Print Product Manual

D.

Release tor Manufacture and Product Available

Questions 38

What is the actual duration as of the status date or data date of Activity B?

PSP Question 38

Options:
A.

7.

B.

3.

C.

0.

D.

4.

Questions 39

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

Options:
A.

Industry publications.

B.

Critical path schedules prepared by you for similar completed projects.

C.

The Petrochemical Industry New Plant Task Duration Handbook.

D.

The cost estimate for the plant prepared by your firm's estimating department.

Questions 40

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

PSP Question 40

Options:
A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

Exam Code: PSP
Certification Provider: AACE International
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Oct 30, 2025