Free The Open Group OG0-093 Practice Exam with Questions & Answers | Set: 13

Questions 121

Complete the sentence by selecting the applicable pair of words. A/an _____is used in Phase A to help identify and understand business _____that the architecture has to address.

Options:
A.

activity model, perspective

B.

business scenario, requirements

C.

use case, interconnections

D.

architecture view, concerns

E.

business transformation readiness assessment, constraints

Questions 122

Which of the following is an objective of the Preliminary Phase?

Options:
A.

Develop a vision of the proposed Enterprise Architecture

B.

Define the process for architecture governance

C.

Create the initial version of the Architecture Roadmap

D.

Document the baseline architecture

E.

Obtain approval for the Statement of Architecture Work

Questions 123

What is used to structure architectural information in an orderly way so that it can be processed to meet stakeholder needs?

Options:
A.

An Architecture Framework

B.

An EA Library

C.

A Content Metamodel

D.

A Stakeholder Map

Questions 124

Which of the following is a re-usable artifact that is used to create architecture models addressing stakeholder concerns?

Options:
A.

Catalog

B.

Matrix

C.

Diagram

D.

View

E.

Viewpoint

Questions 125

Which section of the TOGAF template for Architecture Principles should clearly state the impact to the business and consequences of adopting the principle?

Options:
A.

Implications

B.

Name

C.

Rationale

D.

Statement

Questions 126

NO: 346

Scenario:

Please read this scenario prior to answering the question

Your role is that of a consultant to the Lead Enterprise Architect in a company that speicializes in luxury electric cars and their powertrain components, and also produces battery-charging equipment. It has its own distribution network, its own showrooms, and sells directly to customers via the internet. The company has four manufacturing facilities, two in the North America, one in Europe, and one in Asia.

A challenge that the company is facing to scale up the number of vehicles coming off the production line to meed customer demand, while maintaining quality. At the moment there are supply chain storages for key electronic components related to the autonomous drive system. In response the this, the research arm of the company has pioneered the development of a new self-driving platform. This new design uses common off-the-shelf components that will allow for a significant increase in overall vehicle production. This new design is ready to go into production.

The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. The TOGAF standard is used for developing the automated manufacturing process and systems used to design, manufacture and test the new design. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

As part of putting the new self-driving platform into production, adjustments to the automated assembly processes need to be made. A pilot architecture project at a single location has defined an updated approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and quality.

Refer to the Scenario

The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer’s concern.

Based on the TOGAF standard, which of the following is the best answer?

Options:
A.

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is de

B.

You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed drive assembly at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the a

C.

You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture C

D.

You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architectur