What is one benefit of an Iteration and PI calendar?

Options:
A.

Ability to create a big visible information radiator (BVIR) of the important team and ART milestones

B.

Ability to know the cycle time between important team and ART events

C.

Ability to visualize the ART cadence and synchronization

D.

Ability to ensure that key events do not conflict with non-SAFe events

Scaled Agile SAFe-RTE Premium Access
Questions 62

What does transparency mean in a scrum environment?

Options:
A.

Development and Operations teams work together

B.

The process is visible to all stakeholders

C.

The team is constantly improving its process

D.

Team members must immediately share any and all feedback with each other

Questions 63

Which of the Core Competencies of Business Agility emphasizes a customer-centric ap-proach to defining, building, and releasing a continuous flow of valuable products and services?

Options:
A.

Team and Technical Agility

B.

Enterprise Solution Delivery

C.

Lean Portfolio Management

D.

Agile Product Delivery

Questions 64

What is one action to support a Continuous Integration (CI) culture?

Options:
A.

Make integration results visible

B.

Purchase a CI tool

C.

Secure senior leadership support before starting CI

D.

Follow up with CI ceremonies

Questions 65

During Pl Planning, who owns Feature priorities?

Options:
A.

Release Train Engineer

B.

Solution Architect/Engineer

C.

Product Management

D.

Business Owner

Questions 66

The business must depend on the team for what in order to do any meaningful planning?

Options:
A.

Team capabilities

B.

Commitment to the plan

C.

Measurements

D.

A cross-functional skill set

Questions 67

What is one way to secure stakeholder commitment to the Agile Release Train?

Options:
A.

Provide them a planning schedule outlining a five-year plan for development

B.

Have them estimate User Stories for the teams

C.

Send them the Program Increment (PI) Objectives after each PI Planning event

D.

Have them attend the Program Increment (PI) Planning event