What are personas?

Options:
A.

Descriptions of actual target customers or users

B.

Key end-users the Product Owner leverages for managing the backlog

C.

Fictional representations of target customers or users

Scaled Agile SAFe-RTE Premium Access
Questions 52

Which action describes the behavior of applying Systems Thinking for a Release Train Engineer (RTE)?

Options:
A.

Encourages the team to express opinions in all circumstances

B.

Examines what may be missing to make the environment better for the team

C.

Demonstrates appreciation to team members in many ways

D.

Facilitates individual decision-making over team-level decision-making

Questions 53

Which two behaviors are an important part of the Release Train Engineer role? (Choose two.)

Options:
A.

Drive teams to specific outcomes

B.

Provide answers about Features

C.

Coach leaders to increase alignment

D.

Encourage teams to self-organize

E.

Manage dependencies for teams

Questions 54

Who are two key collaborators with the RTE to support the ART? (Choose two)

Options:
A.

Release Management

B.

System Architects/Engineers

C.

Product Owners

D.

Scrum Masters

E.

Product Management

Questions 55

What best describes what stream-aligned teams do?

Options:
A.

Analyze value streams and transform them using lean-agile principles

B.

Build and deliver customer value with minimal dependencies on other teams

C.

Promote better flow of communications between leadership, trains and teams

D.

Use process-mapping to identify and eliminate process bottlenecks

Questions 56

In addition to Innovation and Planning, what else does the IP Iteration provide time for?

Options:
A.

An estimating guard band

B.

An opportunity to integrate and perform end-to-end testing

C.

Building in quality and compliance

D.

Additional planned work

Questions 57

(What is one action the Release Train Engineer (RTE) can take to facilitate team growth?)

Options:
A.

Provide a team Vision

B.

Encourage continuous learning

C.

Encourage skill specialization

D.

Facilitate conflict

Questions 58

Why is it important for the RTE to understand Tuckman's group dynamic stages?

Options:
A.

The Tuckman four stages should be reflected in the design of the Program Kan-ban

B.

Tuckman helps to better understand Team and ART topologies

C.

The Tuckman dynamic nature of the stages requires that we assume variability and preserve options

D.

An ART is a team of teams and will likely also progress through the Tuckman stages

Questions 59

A Release Train Engineer should build a relationship with which SAFe role in order to ef-fectively assign business value to a team Program Increment (PI) Objective?

Options:
A.

Business Owners

B.

Lean-Agile Leaders

C.

Objective Owners

D.

Solution Managers

Questions 60

Which statement is true about teams?

Options:
A.

Products are more robust when individuals on teams have specific skill sets

B.

Agile Teams can manage daily interruptions

C.

Teams are more productive than the same number of individuals

D.

Changes in team composition do not impact productivity