Free Scaled Agile SAFe-RTE Practice Exam with Questions & Answers

Questions 1

How often should a system demo occur?

Options:
A.

After the end of each program increment (Pl)

B.

After every other iteration

C.

After every release

D.

After every iteration

Scaled Agile SAFe-RTE Premium Access
Questions 2

After an Agile Release Train's first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?

Options:
A.

Ask Product Management and the System Architect what the new Program Back-log looks like just before the next Innovation and Planning (IP) Iteration, so social-ization can begin

B.

Compile all the teams' objectives from PI Planning and send out a summary report

C.

Coach Product Management and the System Architect to include Program Backlog refinement into their cadence-based approach

D.

Ask the Lean Portfolio Management function to hold regular Epic review meetings so new Epics will flow to the Agile Release Train

Questions 3

Product Management has content authority for the Program Backlog including the Vision, the Roadmap, driving the Pl Objectives, and what else?

Options:
A.

Establishing Features and benefit hypotheses

B.

Managing risk, helping to ensure value delivery, and driving continuous improvement

C.

Working with business stakeholders and Solution and System Architects to implement holistic technology across Value Streams

Questions 4

What are two main reasons why the program predictability measure is important? (Choose two.)

Options:
A.

It allows the business and other stakeholders to plan effectively

B.

It identifies under-performing teams

C.

It focuses the Agile Release Train on predictable value delivery

D.

It demonstrates the need to fix the scope at the beginning of the Program Increment (PI)

E.

It indicates whether the Solution is ready to be released

Questions 5

Release Train Engineers have the opportunity to regularly practice and improve which two skills? (Choose two.)

Options:
A.

Servant leadership

B.

Facilitation

C.

Test-driven development

D.

Return on investment projections

E.

Continuous Integration

Questions 6

Program Increment (PI) Objectives should be written in the SMART format. What does the "R" in SMART stand for?

Options:
A.

Realistic

B.

Required

C.

Random

D.

Rationalized

Questions 7

When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?

Options:
A.

That the feature can be completed by that team independently

B.

That the team has not broken the feature into stories yet and has not identified dependencies

C.

That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains

D.

That the team has been assigned, but the feature’ uépendencies have not been identified yet

Questions 8

What are two common PI Planning anti-patterns? (Choose two.)

Options:
A.

Stories are created for the Iterations

B.

The team decides which changes need to happen and when

C.

Too much time is spent analyzing each Story

D.

Scrum Masters who work with multiple teams do not have time for their teams

E.

Too much time is spent prioritizing Features

Questions 9

What best describes what stream-aligned teams do?

Options:
A.

Analyze value streams and transform them using lean-agile principles

B.

Build and deliver customer value with minimal dependencies on other teams

C.

Promote better flow of communications between leadership, trains and teams

D.

Use process-mapping to identify and eliminate process bottlenecks

Questions 10

What are personas?

Options:
A.

Descriptions of actual target customers or users

B.

Key end-users the Product Owner leverages for managing the backlog

C.

Fictional representations of target customers or users