Free PRINCE2 PRINCE2-Agile-Foundation Practice Exam with Questions & Answers | Set: 4

Questions 31

Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

Options:
A.

It reduces testing in order to meet deadlines

B.

It sets the project baseline at the correct level

C.

It enables team dynamics to remain the same

D.

It improves the supplier's reputation with the customer

PRINCE2 PRINCE2-Agile-Foundation Premium Access
Questions 32

In which workshop are the project role descriptions created?

Options:
A.

Starting-up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Project canvas workshop

Questions 33

Which statement about the ‘directing a project’ process is CORRECT?

Options:
A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

Questions 34

Which is a purpose of the quality theme?

Options:
A.

To define the specific conditions that enable a product to be usable

B.

To determine how the means of delivering products is communicated

C.

To evaluate whether the project continues to be achievable

D.

To assess any potential improvements to a product

Questions 35

Which TWO statements about the supplier subject matter expert are CORRECT?

1) They provide a wider picture of the customer view.

2) They prioritize requirements at the detailed level.

3) They should be focused on the customer.

4) They ensure that the work is compliant with project standards.

Options:
A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Questions 36

Which statement about the waterfall methodology definition is CORRECT?

Options:
A.

It states that deadlines should not be moved

B.

It has distinct goals for each stage of development

C.

It is a behavior that involves making things transparent

D.

It promotes the use of experiments carried out in a scientific way

Questions 37

Which of the following BEST describes stakeholders in a project?

Options:
A.

Those who have a formal role in the project team

B.

Those who will use project products

C.

Those who can affect or be affected by the project

D.

Those who can impact the project

Questions 38

Which technique is used in the ’Issues' practice?

Options:
A.

Trading/swapping

B.

Objectives and key results

C.

Refactoring

D.

Delegation poker

Questions 39

Which should be an objective of a retrospective?

Options:
A.

To identify many process improvements and implement them

B.

To identify key process improvements to implement in the next sprint

C.

To encourage the team to bond by allowing social activities to take place

D.

To focus on objective learning rather than subjective feelings and emotions

Questions 40

What is the purpose of the 'progress' practice?

Options:
A.

To provide a forecast for the project's viability

B.

To identify and assess opportunities and threats

C.

To identify the user needs and requirements

D.

To establish accountability for the project

Certification Provider: PRINCE2
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Mar 6, 2026
Questions: 162