Free PRINCE2 PRINCE2-Agile-Foundation Practice Exam with Questions & Answers | Set: 3

Questions 21

Which of the following describes shared attitudes, values, and goals?

Options:
A.

Culture

B.

Leadership

C.

Co-creation

D.

Management

PRINCE2 PRINCE2-Agile-Foundation Premium Access
Questions 22

In Scrum, what answers the question ‘what can be done this sprint?’

Options:
A.

Daily scrum

B.

Sprint review

C.

Sprint planning

D.

Increment

Questions 23

What is a role of personas in the 'business case' practice?

Options:
A.

To group users based on demographic data

B.

To ensure project timelines are met

C.

To identify and articulate specific user benefits

D.

To differentiate between product versions

Questions 24

Which BEST describes the senior user role when tailoring the organization theme?

Options:
A.

An ‘agile sponsor’

B.

An ‘executive sponsor’

C.

A ‘coach’

D.

A ‘super product owner’

Questions 25

What is a purpose of the 'project closure' workshop?

Options:
A.

Align teams with project vision

B.

Create benefits management approach

C.

Update the project documentation

D.

Refine the release map for the next stage

Questions 26

Which statement about the ‘protect the level of quality’ target is CORRECT?

Options:
A.

It is achieved by ensuring that all features are delivered

B.

It is unlikely to be achieved if incomplete user documentation is provided

C.

It allows change at the detailed level to be handled dynamically

D.

It avoids the use of extra people to improve progress during a timebox

Questions 27

Which statement about the ‘embrace change’ target is CORRECT?

Options:
A.

It re-establishes team dynamics when a new member joins the team

B.

It trades user stories for those of a similar size

C.

It results in the late delivery of the minimum viable product

D.

It degrades the performance of the features that are delivered

Questions 28

What needs to happen when new detailed requirements are added to a timebox?

Options:
A.

Requirements of a similar level of effort should be removed

B.

More people should be added to the delivery team

C.

The delivery milestones should be reviewed and re-planned

D.

Formal change control should be applied

Questions 29

Which of the following is used to monitor progress?

Options:
A.

Delegation matrix

B.

Swarming

C.

T-shirt sizing

D.

Burn-down chart

Questions 30

Which well-known agile method uses visualization, and controls work in progress?

Options:
A.

Scrum

B.

Lean Startup

C.

Lean

D.

Kanban

Certification Provider: PRINCE2
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Sep 13, 2025
Questions: 132

PRINCE2 Free Exams

PRINCE2 Free Exams
Examstrack provides free PRINCE2 exam prep materials and practice tests to support your PRINCE2 certification goals.