Questions 31

While quality checking the user stories, the team looks for the component that defines the boundary of the user story and assists with validating the delivered functionality. They are checking for the:

Options:
A.

Iteration ' s associated vision

B.

Value statement

C.

Acceptance Criteria

D.

Title

IIBA IIBA-AAC Premium Access
Questions 32

The team is assessing feedback from the work that’s been completed. After some discussion they realize this feedback can be used to assess the remaining components that are yet to be built. Specifically, this feedback can be used to help them determine if the initiative’s remaining solution components are:

Options:
A.

Impacting other initiatives

B.

Supported by management

C.

Likely to be completed

D.

Still appropriate

Questions 33

The delivery team is in a meeting and reviewing various solution alternatives. Specifically, they are discussing the appropriate time for decision making and the value that could be delivered. They are applying the following technique:

Options:
A.

Value stream mapping

B.

Backlog management

C.

Story mapping

D.

Real options

Questions 34

When reviewing the initiative, the team has determined that the solution is not delivering the desired outcomes or sufficient value. A viable option to consider is:

Options:
A.

Release the product

B.

Cancel the initiative

C.

Restart the work

D.

Assign to a new team

Questions 35

Although the work for the initiative has begun, there is still some confusion about what is being built by the delivery team. After some discussion about how to address this, the team decides to complete a:

Options:
A.

Planning workshop

B.

Retrospective

C.

Estimation workshop

D.

Plan review

Questions 36

The team agrees that the agile business analysis principle of “see the whole” aligns with the BACCM core concept of:

Options:
A.

Value

B.

Stakeholder

C.

Needs

D.

Context

Questions 37

After much discussion, the team decides to represent the goal and scope of an initiative with images and words using the following technique:

Options:
A.

Visioning

B.

Kano Analysis

C.

Personas

D.

Job Stories

Questions 38

At the Strategy Horizon, effective analysis work can help stakeholders make sound decisions by:

Options:
A.

Continually improving team processes that lead to higher performing teams

B.

Providing research reports that identify emerging technology

C.

Assessing progress of current initiatives against their planned budgets

D.

Interpreting new information and identifying what ' s important

Questions 39

The team is trying to determine how to best measure the success of the outcomes they produce. After some discussion, they decide success is measured by the value derived from the solution and:

Options:
A.

The number of conversations with stakeholders

B.

How closely the plan is followed

C.

How well new needs are uncovered

D.

How well it satisfies customers ' needs

Questions 40

While discussing the Business Analysis Approach, decisions are made about which methodology or approach to use for the initiative being considered. These discussions are happening at the:

Options:
A.

Feedback horizon

B.

Initiative horizon

C.

Strategy horizon

D.

Delivery horizon