Free IIBA IIBA-AAC Practice Exam with Questions & Answers | Set: 2

Questions 11

The team is making important decisions when assessing the initiative they are working on. Feedback received from the Delivery Horizon informs:

Options:
A.

Priority and sequencing of solution components

B.

Identification of reporting requirements

C.

Suggestions for team process continuous improvement

D.

How to build the required solution components

IIBA IIBA-AAC Premium Access
Questions 12

A team demonstrating the following characteristics:

Expects rapid change

Incorporates learning & feedback

Has a preference for shorter time frames

Treats plans as testable hypothesis

is following planning practices that are described as:

Options:
A.

Predictive and adaptive

B.

Adaptive and hypothesis

C.

Iterative and predictive

D.

Iterative and adaptive

Questions 13

The delivery team discusses how to maintain the integrity of their backlog items. They decide to?

Options:
A.

Delay changes until they are caught up

B.

Develop a business case for all changes

C.

Monitor stories and features for staleness

D.

Ensure all changes are approved

Questions 14

While using Kano Analysis to determine what features to include in the MVP, the delivery team decides to include characteristics which if omitted will cause intense dissatisfaction. A team member indicates that these are referred to as:

Options:
A.

Performance characteristics

B.

Threshold characteristics

C.

Minimum characteristics

D.

Excitement characteristics

Questions 15

The team is struggling with how to best design and explore options for moving forward. They settle on a time-boxed research approach which is often referred to as a:

Options:
A.

Simulation

B.

Wasteful

C.

Spike

D.

Incremental

Questions 16

In the past, a team has been unable to deliver solutions in a timely manner and they feel this is due to the customer being unable to decide what they want. The team has decided to ask the customer to “sign-off” on their requirements. This violates the following value statement:

Options:
A.

Individuals and interactions over process and tools

B.

Prioritizing outputs over outcomes

C.

Working solutions over comprehensive documentation

D.

Customer collaboration over contract negotiation

Questions 17

While working at the Strategy Horizon, one of the key decisions to make upfront is:

Options:
A.

Is a need worth satisfying?

B.

What features should we deliver?

C.

Have we delivered enough value?

D.

Should we cancel the work?

Questions 18

The delivery team is discussing how to achieve the strategic goals for their work. They determine the following analysis technique is important to help the team maintain its focus:

Options:
A.

Relative estimation

B.

Spikes

C.

Story elaboration

D.

Visioning

Questions 19

After some debate the delivery team decides to use the product roadmap because it will help them:

Options:
A.

Align strategy to goals

B.

Maintain defined scope

C.

Keep the team on schedule

D.

Align increments with product vision

Questions 20

The team is considering which of several solution paths they should invest in. They are working only from conjecture and opinion, not data and facts. A practitioner with an agile mindset would remind them to:

Options:
A.

Perform a value analysis of real options

B.

Discover what works by trying things out

C.

Consider analysis at multiple horizons

D.

Collaborate more to create new ideas

Exam Code: IIBA-AAC
Certification Provider: IIBA
Exam Name: IIBA Agile Analysis Certification
Last Update: Jul 10, 2025
Questions: 85
PDF + Testing Engine
$164.99
$66
Testing Engine
$124.99
$50
PDF (Q&A)
$104.99
$42