Questions 21

A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?

Options:
A.

Document

B.

Proof

C.

Approval

Adobe AD0-E911 Premium Access
Questions 22

A project owner creates a project with the Schedule Mode set to Start Date.

Which task constraint is the default when creating new tasks in this scenario?

Options:
A.

As Soon As Possible

B.

As Late As Possible

C.

Must Start On

Questions 23

What parent object can have child objects?

Options:
A.

Issue

B.

Project

C.

Portfolio

Questions 24

A project manager is managing a project and realizes a task is delayed. They want to see how downstream tasks are impacted.

Which feature of the Gantt chart will help them understand this?

Options:
A.

Actual Dates

B.

% Complete

C.

Critical Path

Questions 25

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:
A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Questions 26

Which two options are available with Workfront reports? (Choose two.)

Options:
A.

A chart report that references a multi-select custom field

B.

Planned date-based calendar reports

C.

Filters with a custom grouping

D.

An object name with more than 500 characters

Questions 27

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

Options:
A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.

B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.

C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.

Questions 28

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

Options:
A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.

Exam Code: AD0-E911
Certification Provider: Adobe
Exam Name: Adobe Workfront Project Manager Certified Professional
Last Update: May 9, 2026
Questions: 95
PDF + Testing Engine
$164.99
$49.5
Testing Engine
$124.99
$37.5
PDF (Q&A)
$104.99
$31.5