Pre-Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70track

Free Adobe AD0-E911 Practice Exam with Questions & Answers

Questions 1

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer ' s time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?

Options:
A.

Utilization

B.

Workload Balancer

C.

Hours

Adobe AD0-E911 Premium Access
Questions 2

Which field is used to create a milestone step on a milestone path in the Setup area?

Options:
A.

Status

B.

Description

C.

Key

Questions 3

A project manager compares the original schedule for a task to another set of dates that moved later after predecessors slipped and the assignee changed a completion commitment.

What do these later, system-calculated dates represent?

Options:
A.

They are Planned Dates that show the originally scheduled task dates.

B.

They are Projected Dates that show the current forecast for task start and finish.

C.

They are Milestone Path Dates that show when milestone tasks are expected to occur.

Questions 4

A project manager would like to assign tasks across projects to a team without having to navigate to each project.

How can the project manager do this?

Options:
A.

Assign work using the Resource Planner.

B.

Assign work by drag-and-drop.

C.

Assign work in bulk.

Questions 5

What item, when shared with a user, can never give that user inherited permission to a project?

Options:
A.

Portfolio

B.

Task

C.

Report

Questions 6

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Options:
A.

Projected Date

B.

Planned Date

C.

Estimated Date

Questions 7

A project manager is updating a project in Workfront that is behind schedule.

Which action could be taken so that all tasks are completed by the requested completion date?

Options:
A.

Give all tasks a Task Constraint of “Must Start On”

B.

Reduce the durations of the tasks.

C.

Adjust all of the Planned Start Dates to the same day.

Questions 8

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

Options:
A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.

B.

Add a new billing rate to all tasks that involve video editing.

C.

Add a new billing rate within the project.

Questions 9

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

Options:
A.

Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.

B.

Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.

C.

In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.

Questions 10

Which project status defaults the project condition to On Target?

Options:
A.

In Progress

B.

Idea

C.

New

Exam Code: AD0-E911
Certification Provider: Adobe
Exam Name: Adobe Workfront Project Manager Certified Professional
Last Update: May 9, 2026
Questions: 95
PDF + Testing Engine
$164.99
$49.5
Testing Engine
$124.99
$37.5
PDF (Q&A)
$104.99
$31.5