What is the minimum percentage reduction from the baseline required to earn the exemplary performance point for the Indoor Water Use Reduction Credit, Option 2?
An equipment upgrade requires an initial investment of $1,500.00 USD with a total annual savings of $500.00 and a 33% rate of return. What is the Simple Payback Period for this improvement?
A building manager changes the sequence of operation for boilers to better match heating demand as a result of an ASHRAE Level 2 analysis. Which of the following is an example of an appropriate topic for training of building operations staff to continue implementation of this change and meet the requirements of Energy and Atmosphere Credit, Existing Building Commissioning - Implementation?
Which of the following plumbing fixtures apply to the calculations in Water Efficiency Prerequisite Indoor Water Use Reduction?
What is the maximum number of points possible for the Exemplary Performance option of the Innovation Credit, Innovation?
Calculator
Which of the following alternative transportation strategies help reduce pollution and land development effects from automobile use?
What is the allowed maximum tenant space exclusion for Energy and Atmosphere Prerequisite, Minimum Energy Performance?
A new office building was LEED Gold certified, and the tenants have occupied the space for one month. The property manager would like to certify the building under LEED for Building Operations and Maintenance: Existing Buildings.
What program requirements apply?
Landscape irrigation practices consume large quantities of potable water. By evaluating the project's outdoor water
budget and irrigation water demand early in the Establishment Period in Water Efficiency Credit, Outdoor Water Use
Reduction project teams will be able to
What public health risk must be balanced with water efficiency and chemical usage in every water treatment program?