Big Halloween Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Free Exin CDCS Practice Exam with Questions & Answers | Set: 2

Questions 11

You are working on the design of a new facility. The electrical riser of the building with high current power is located close to the area where sensitive IT equipment in the computer room will be located.

What should you recommend to reduce the amount of EMF coming from the electrical riser?

Options:
A.

Install single-phase power cabling

B.

Install three-phase power cabling based on three individual core wires

C.

Install bus bar trunking

D.

Install three-phase power cabling based on a combined cable (e.g. XLPE etc.)

Exin CDCS Premium Access
Questions 12

What mainly affects the cooling capacity of a raised floor tile?

Options:
A.

Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle

B.

Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile

C.

Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

D.

Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile

Questions 13

The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.

What action, if any, should you recommend for the computer room?

Options:
A.

Maintain the current wet pipe system.

B.

Replace the wet pipe system with a deluge system.

C.

Replace the wet pipe system with a dry pipe system.

D.

Replace the wet pipe system with a pre-action system.

Questions 14

A new facility requires electrical distribution of 100A to be installed in the computer room, 1 m (3 ft) above sensitive IT equipment. What type of system minimizes EMF impact?

Options:
A.

Install single-phase power cabling

B.

Install three-phase power cabling based on three individual core wires

C.

Install bus bar trunking

D.

Install three-phase power cabling based on a combined cable (e.g., XLPE)

Questions 15

A customer requires THDi from the UPS not to exceed 3% and wants high efficiency. The UPS has a 6-pulse SCR/thyristor rectifier and is loaded ~80%. Many ICT changes are expected in the next 3 years. What should you recommend?

Options:
A.

Nothing; the UPS will keep THDi at the right levels

B.

Install a passive harmonic filter on the UPS

C.

Install an active harmonic filter on the UPS

D.

Install an isolation transformer rated K13 or K20

Questions 16

Do you need to consider blast protection when designing a data center?

Options:
A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Questions 17

You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.

Options:
A.

12 Amperes

B.

30 Amperes

C.

60 Amperes

D.

80 Amperes

Questions 18

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

Options:
A.

PUE does not indicate efficiency

B.

Data center A

C.

Data center B

D.

Data center C

Questions 19

Which formula is correct?

Options:
A.

Phase-to-Neutral Voltage = Phase-to-Phase voltage * 1.732

B.

Phase-to-Neutral Voltage = Phase-to-Phase voltage /1.732

C.

Phase-to-Neutral Voltage = Phase-to-Neutral voltage * 1.732

D.

Phase-to-Neutral Voltage = (Phase-to-Phase voltage * 1.732) / Phase-to-Neutral Voltage

Questions 20

When installing a raised floor, can we use a spirit level bar to level the floor?

Options:
A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.