Free Exin CDCS Practice Exam with Questions & Answers | Set: 3

Questions 21

An MCB needs to be installed in the PDU of an ICT rack. Which breaking curve should you select?

Options:
A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

Exin CDCS Premium Access
Questions 22

Where should perforated tiles be installed?

Options:
A.

At the back of racks

B.

Every 5th rack

C.

One tile per rack in front

D.

As close to AC as possible

Questions 23

The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.

Taking energy efficiency as the highest priority, which cooling system should you recommend?

Options:
A.

Standard air conditioning units, as spares might not be readily available

B.

Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment

C.

Waterside economizer

D.

Airside economizer

Questions 24

When are the wet bulb and dry bulb temperatures identical?

Options:
A.

When the dry bulb's temperature is at the lowest allowable temperature for IT equipment as per ASHRAE

B.

When the dry bulb's temperature is at the highest allowable temperature for IT equipment as per ASHRAE

C.

When the relative humidity is at the best practice value for relative humidity, being 50% RH

D.

When the relative humidity is 100%

Questions 25

Should aerosol cleaning solutions be used in the computer room?

Options:
A.

No, unless leak detection installed

B.

No, it will contaminate the room

C.

Yes, only if room smells bad

D.

Yes, if not connected to power

Questions 26

What indicates the overcurrent of a fuse or breaker?

Options:
A.

The maximum inrush current an overcurrent protection device can handle within a defined period of time

B.

The maximum electrical current which can flow in a particular electrical system under short-circuit conditions; it is determined by the voltage and impedance of the supply system

C.

The current at which the device will trip

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electrically damaging arc

Questions 27

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:

•Rated power: 30 kVA

•Rectifier input voltage: 400 V/3 phase

•Rectifier input power factor: 0.8

•Battery rated voltage: 384 V

•Number of cells: 192

•End of discharge voltage: 308 V

•Inverter output voltage: 400 V/3 phase

•Inverter output power factor: 0.8

What information is missing to perform the battery calculation?

Options:
A.

UPS efficiency

B.

Inverter efficiency

C.

Load imbalance on the phases

D.

Available battery charging current

Questions 28

It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.

Where should you recommend the shielding material to be installed?

Options:
A.

As close as possible to the computer room

B.

As close as possible to the transformer room

C.

It does not matter, either close to the transformer room or the computer room is okay as there is no impact to cost or shielding material performance

D.

Shielding is not required to be installed as 100mG is within the acceptable levels for computer rooms

Questions 29

Management requests a 15-minute battery bank at full UPS load. UPS specs:

    30 kVA, PF 0.8

    Battery 384 V (192 cells), end discharge 308 V

    Inverter PF 0.8, 400 V output

What information is missing to perform the calculation?

Options:
A.

UPS efficiency

B.

Inverter efficiency / output PF

C.

Load imbalance

D.

Available battery charging current

Questions 30

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

Options:
A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.