Big Halloween Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Free Exin CDCS Practice Exam with Questions & Answers

Questions 1

What is the redundancy setup shown in the diagram?

Options:
A.

2+N+1

B.

N+2

C.

N+N+N

D.

2(N+1)

Exin CDCS Premium Access
Questions 2

Smoke sensors must be installed in the computer room. What is the minimum density?

Options:
A.

1 per 5 m²

B.

1 per 10 m²

C.

1 per 25 m²

D.

1 per 40 m²

Questions 3

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

Options:
A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Questions 4

What is the effect of having a damper (in open position) construction in a raised-floor tile?

Options:
A.

Dampers allow for a higher supply air temperature

B.

Dampers increase the air volume by approximately 10%

C.

Dampers reduce the air volume by approximately 10%

D.

Dampers can be used when there is a high rate of temperature change in the computer room

Questions 5

When designing a data center network, your company wants to minimize the number of network cables to install. What type of physical cabling layout would be the best choice?

Options:
A.

Top of Rack (ToR) design

B.

End of Row (EoR) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Questions 6

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

Options:
A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators will run all the time

Questions 7

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

Options:
A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings

Questions 8

An air-conditioner unit needs to be selected. Two types are available:

Unit-A has a Sensible Heat Ratio (SHR) of 0.7.

Unit-B has a Sensible Heat Ratio (SHR) of 0.9.

From an efficiency point of view, which one should be selected?

Options:
A.

It does not matter, as the Sensible Heat Ratio has nothing to do with efficiency.

B.

Not relevant, as Sensible Heat Ratio is only specified for air-conditioner equipment to indicate the ratio between intake temperature and exhaust temperature.

C.

Unit A

D.

Unit B

Questions 9

What is the sensible heat ratio (SHR)?

Options:
A.

Ratio of the sensible heat to the total of sensible plus latent heat to be removed from a conditioned space

B.

Ratio of the latent heat to the total of sensible plus latent heat to be removed from a conditioned space

C.

Ratio of cold-air supply to hot-air return temperature of a cooling system

D.

Ratio of the cold-aisle temperature to the hot-aisle temperature

Questions 10

What is the calculation for the desired attenuation factor for shielding material?

Options:
A.

A = 20 log (M / R)

Where

A is Attenuation

M is the maximum acceptable value

R is the real value measured

B.

A = M / R

Where

C.

A is Attenuation

M is the maximum acceptable value

R is the real value measured

D.

A = 20 log (R / M)

Where

A is Attenuation

R is the real value measured

M is the maximum acceptable value

E.

You do not have to calculate the attenuation factor for shielding material as it always has the same attenuation