Free CIPS L4M3 Practice Exam with Questions & Answers

Questions 1

In a contract, express terms and implied terms may contradict on the same issues. Under which of the following circumstances, implied terms will override express terms?

Options:
A.

Implied terms are created by trade customs

B.

Contracting parties are silent on a matter that was not included in express terms

C.

No circumstances. Express terms always take precedence over implied terms

D.

Implied terms are created by law which prevents them to be overridden

CIPS L4M3 Premium Access
Questions 2

XYZ Ltd and Engineer Corp signed a long-term supply contract in which both parties had agreed on performance targets. Recently, due to increased customer demands, XYZ Ltd realises that they should make changes to the contract with Engineer Corp with regards to performance management. These changes are approved and signed by both the buyer and seller. The changes to the contract are known as...?

Options:
A.

An amendment to the prime contract

B.

A stand-alone subcontract to the prime contract

C.

An appendix to the prime contract

D.

A separate counter-offer to the supplier

Questions 3

Which of the following are likely to be advantages of using request for quotation? Select TWO that apply:

Options:
A.

Lower administration costs

B.

Short turnaround times

C.

No specification required

D.

Helping the buying organisation assess both price and quality

E.

Encouraging suppliers to submit creative solutions

Questions 4

A tire manufacturer entered into a contract with a distributor. In the contract, the distributor is prohibited from selling the tire under the price list. The distributor must pay $5 for each tire sold in breach. The amount of $5 is known as...?

Options:
A.

Penalty

B.

Quantum meruit

C.

Liquidated damages

D.

Caveat Emptor

Questions 5

Which of the following KPIs is qualitative?

1. Openness and co-operation of supplier

2. Responsiveness of supplier

3. Customer satisfactory ratings

4. Cost management

5. OTIF deliveries

Options:
A.

2 and 5 only

B.

1 and 3 only

C.

2 and 3 only

D.

1 and 4 only

Questions 6

Which of the following best defines an ‘express’ term in general contract arrangements?

Options:
A.

It is a standard set of terms and conditions published by CIPS

B.

It is not necessarily discussed by the parties, but nonetheless forms part of the contract

C.

It is the term that is added to the contract by the law or based upon the facts of the case.

D.

It is clearly agreed between the parties, and is virtually always written down in the contract

Questions 7

Company A buys a lorry from Company B on hire purchase. During the contractual period, Company A makes default in paying the instalment. Company B has...?

Options:
A.

The right to take repossession of the lorry

B.

The option to repossess the lorry

C.

No right to take repossession

D.

Company B has to approach the court

Questions 8

What are disadvantages of a buyer contracting on the supplier's terms? Select TWO that apply.

Options:
A.

Materials will not be changed without the buyer’s consent

B.

The buyer would not be subject to any indemnity clause obligations

C.

Title to goods may remain with the supplier until payment is received

D.

Goods received late will incur penalties for the supplier

E.

Prices may increase without notification to the buyer

Questions 9

Maximum Score 1

A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a ‘model form contract’?

Options:
A.

It avoids the requirement to create complex contracts each time but can be adapted to suit particular circumstances

B.

Formulae or indices can be included to assess any additional supplier’s claims for contract price adjustment

C.

Incentive payment terms can be included to reward the supplier for attainment of cost savings

D.

Legal advice is still required if significant amendments or variations are to be made to the contract

Questions 10

Maximum Score 1

Procurement professionals must have an awareness of labour standards and environmental, social and governance issues when contracting with suppliers. Which TWO of the following are relevant for consideration?

Options:
A.

Indemnity

B.

Warranty

C.

Modern Slavery

D.

Sustainability

E.

ISO 9000 accreditation

Exam Code: L4M3
Certification Provider: CIPS
Exam Name: Commercial Contracting
Last Update: Dec 14, 2025
Questions: 233

CIPS Free Exams

CIPS Free Exams
Access free CIPS exam study guides and practice tests at Examstrack. Ensure your success with top-notch preparation resources at Examstrack.