Free BICSI RCDD-002 Practice Exam with Questions & Answers | Set: 5

Questions 41

Which of the following is NOT an example of a perimeter pathway?

Options:
A.

Furniture pathways

B.

Surface raceways

C.

Multi channel raceways

D.

Under carpet cabling

E.

Raceways integrated within walls

BICSI RCDD-002 Premium Access
Questions 42

Assuming the total fill capacity of a pathway is 100 cables (all of the same cable type and size), the MAXIMUM number of cables to be installed during the initial installation, without exceeding the fill ratio is:

Options:
A.

25

B.

40

C.

50

D.

60

Questions 43

In a run requiring 15 m (50 ft) of cable between the floor distributor and the consolidation point, the MAXIMUM length of cable allowed between the CP and the telecommunications outlet is:

Options:
A.

27.4 m (90 ft)

B.

36.5 m (120 ft)

C.

45.8 m (150 ft)

D.

75 m (242 ft)

E.

90 m (295 ft)

Questions 44

Which of the following is NOT a type of connector for optical fiber?

Options:
A.

LC

B.

ST

C.

SFF

D.

S/FTP

E.

SC

Questions 45

When installing outlet boxes in ten private offices in an area which may prove to be difficult to install future additional telecommunications outlets, the MINIMUM quantity of outlet boxes that should be installed is:

Options:
A.

10

B.

20

C.

30

D.

Based on the type of cabling specified

Questions 46

Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below:

2 Technician

2.1 Install cabling

2.2 __________

2.3 Activate wireless

Options:
A.

Install access point

B.

Clean work area

C.

Install pathway for cabling

D.

Confirm wireless coverage

Questions 47

Exhibit:

RCDD-002 Question 47

If a work breakdown structure (WBS) shows the tasks below, what is C, the successor task?

A) Install OSP pathways

B) Install fiber

C) ________.

Options:
A.

Hold inspection

B.

Create budget

C.

Conduct safety meeting

D.

Perform site survey

Questions 48

Which is NOT true about conformance quality?

Options:
A.

It focuses on physical quality.

B.

It involves evaluating customer satisfaction.

C.

It requires work force training.

D.

It includes inspections of work.

E.

It follows the principle of plan, do, check, and act.

Questions 49

Which is NOT a type of contract?

Options:
A.

Contractor submits a fixed price for the SOW

B.

Contractor is reimbursed for actual costs plus a fee

C.

Unit price is used because the SOW cannot be determined prior to bid

D.

Mediation panel assigns a fair price based on work completed

Questions 50

A scope of work should contain all of the following EXCEPT:

Options:
A.

Request for purchase

B.

Project schedule

C.

Project objective

D.

Assumptions

E.

Customer needs