Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
Which 2 actions should the Workshop Facilitator take to implement the new
Must Have requirement?
A difference of opinion on the outcome of an earlier project has created a
' them and us ' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully
meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture
Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall ' s
specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,
until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
Maintainability is a required attribute of the initial delivered solution
Deliver first, re-engineer later
Short-term, tactical solution

Which 2 statements explain why the Architecture Angels ' Marketing Director would be an appropriate Business Visionary?
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
|