Free APMG-International AgilePM-Practitioner Practice Exam with Questions & Answers | Set: 2

Questions 11

Which statement should be recorded under the High-level timing considerations heading?

Options:
A.

The traditional market has changed over the last year and UniCo can no longer rest on its previous success.

B.

UniCo lost significant market share in the last six months and faces ongoing increased competition in the next year.

C.

UniCo’s new finance system was delivered in the last quarter and training in the new system is almost complete.

D.

Completing the large contract with a Utilities company over the next nine months is a vital step to achieving the end vision.

APMG-International AgilePM-Practitioner Premium Access
Questions 12

Sales staff are unhappy that they have been told that they will lose the Sales relaxation area completely to make space for the new Selco staff. The Sales staff are considering consulting their Union about escalating their discontent.

Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?

Options:
A.

Arrange joint workshops for Sales and Selco staff to develop ideas and comment on layout options.

B.

Delay information on the impact of the Selco relocation on Sales staff until just before the relocation move occurs.

C.

Exert pressure on the Sales management team to make sure any resistance is kept ‘quiet’.

D.

Provide a farewell gathering in the relaxation area to enable staff to remember past stories about the area.

E.

Organize a Sales discussion group to look at alternative relaxation facilities that could be provided to the Sales staff.

Questions 13

For cognitive learning, which is the BEST example of providing ' learning feedback ' ?

Options:
A.

Giving supervisor feedback on return to work.

B.

Testing before and after learning.

C.

Reviewing learners’ ideas in a group discussion.

D.

Discussion at the learners ' next annual performance reviews.

Questions 14

Which statement should be recorded under the Change Management Team and Relationships heading?

Options:
A.

The training available to UniCo staff needs to be realigned to include mobile application technology, so that the necessary skills are developed to support customers.

B.

The CEO seems to be a little concerned about taking the company in a different direction and his reservations need to be addressed.

C.

The Project Management Office has offered to provide support in planning, scheduling, monitoring, and control.

D.

The Sales staff need to understand how the changes will lead to greater opportunities for increased commissions before they are likely to participate.

Questions 15

The Web Content Manager has provided the Web Developer with a mock up

of the ' Contact Us ' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads ' Delete ' instead of ' Cancel ' .

What action should the Web Content Manager take?

Options:
A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Questions 16

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:
A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Questions 17

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

Options:
A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Questions 18

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:
A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Questions 19

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

Options:
A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company ' s revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Questions 20

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:
A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.