Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.
Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?
How should the Project Manager assist the electricians to deliver the wiring?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
At the beginning of Solution Development Timebox A, the Timebox is being
planned in detail. Although Foundations was conducted at a high level, the
Prioritised Requirements List was baselined. Now the Solution Development
Team is setting detailed acceptance criteria against each requirement.
Is this an appropriate approach to setting detailed acceptance criteria?
Which 2 statements represent appropriate entries for the plan for Post-Project
activities?
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
A difference of opinion on the outcome of an earlier project has created a
'them and us' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
Which 2 actions should the Team Leader take to implement the new Must
Have requirement?