Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free APMG-International AgilePM-Practitioner Practice Exam with Questions & Answers

Questions 1

During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent

any Planning Authority issues.

Is this an appropriate application of Agile Project Management for this project?

Options:
A.

Yes, because all stakeholders should attend the Daily Stand-up meetings.

B.

Yes, because each team member will have an opportunity to highlight any Planning Authority issues that may otherwise hinder their progress.

C.

No, because NOT all members of the Solution Development Team will attend the Daily Stand-up.

D.

No, because only members of the Solution Development Team should be permitted to attend Daily Stand-up meetings.

Questions 2

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.

Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully

meet Hoy Hall requirements, after deployment.

2. Developing a fully functioning in-house system, developed and hosted by Architecture

Angels IT Operations team.

3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's

specification.

4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,

until a suitable system can be implemented at the site.

5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.

Column 2

    Maintainability is a required attribute of the initial delivered solution

    Deliver first, re-engineer later

    Short-term, tactical solution

AgilePM-Practitioner Question 2

Options:
Questions 3

Answer the following questions about the tracking and control activities carried out within the project.

Decide whether each activity has been applied appropriately and select the response that supports your decision.

During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager

organized a Facilitated Workshop with the project team to discuss and agree the requirements.

Is this an appropriate application of Agile Project Management for this project?

Options:
A.

Yes, because discussing requirements in the presence of project stakeholders will promote communication and buy-in.

B.

Yes, because this will allow each team member working in a Timebox to raise any issues which may hinder their progress.

C.

No, because early and frequent delivery of the product features will on its own be sufficient to maintain engagement with the stakeholders.

D.

No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders'

expectations.

Questions 4

The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-

rounds of the new bedroom and en-suite bathroom facilities throughout the project.

Is this an appropriate application of Agile Project Management for this project?

Options:
A.

Yes, because the early and frequent demonstration of product features to the Business Sponsor increases the visibility of the project and keeps the business engaged.

B.

Yes, because the project's budget holder is the only person who can approve project products.

C.

No, because products should be handed over at the end of the project, during Post-Project.

D.

No, because the Daily Stand-up meetings should have allowed the key representatives to review and discuss the evolving solution.

Questions 5

Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?

Options:
A.

Is a friend of the Architecture Angels' Chief Executive.

B.

Is fully committed to changing the company's strategic direction to include hotel renovation.

C.

Is one of the original four founders of the company.

D.

As a Director, will ensure that the project is NOT driven by the cost-consciousness of the Finance Director in the role of Business Sponsor.

E.

Has a passion for old buildings and can see the potential for business opportunity.

Questions 6

Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

AgilePM-Practitioner Question 6

Assertion:-

1. The rooms and facilities must be deployed into live use at the end of each Timebox.

BECAUSE

Reason:

Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.

2. The tasks associated with each Solution Development Timebox should be included

in the Delivery Plan.

BECAUSE

Reason:

A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.

3. The development approach should have been agreed during Foundations.

BECAUSE

Reason:

The Development Approach Definition must be created before Evolutionary

Development can commence.

4. The resources from Timber Tigers and Earth Excavations should have been engaged

before the start of Evolutionary Development.

BECAUSE

Reason:

Commitment to delivery is based on pre-agreed resource levels at the project level.

5. A final Deployment phase should be held after Timebox C has completed.

BECAUSE

Reason:

The Deployed Solution is assessed post-project to confirm whether the expected benefits have been

achieved.

AgilePM-Practitioner Question 6

AgilePM-Practitioner Question 6

Options:
Questions 7

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

Options:
A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Questions 8

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?

Options:
A.

Paper-based drawings are to be used for each option being considered for the building and gardens.

B.

The SAD must include a physically-built miniature model of the Hoy Hall building.

C.

The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.

D.

The views of the 'Hoy for Hoy Hall' Action Group members are NOT relevant to the business decision made by Architecture Angels' Finance Director when approving the final option.

E.

The SAD should contain high-level costs for all elements of each solution option.

Questions 9

The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to

simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was

potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a

customer financial transaction.

Answer the following question about the actions to be taken by each role.

Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,

select from Column 2 the role that should carry out the action.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

    Advise how the legislation on the transfer of data will affect the requirements

and the system.

    Agree the changes needed to the corporate technical architecture with the

Architecture Angels IT support team.

    Ensure the information security vulnerability is communicated to the AA Head

Office IT Director.

    Evaluate the impact of proposed security controls on the business and decide

on the most suitable solution.

    Reprioritise the requirements on the Prioritised Requirements List associated

with the security issue.

Column 2

    Project Manager

    Business Sponsor

    Business Visionary

    Technical Coordinator

    Business Analyst

    Team Leader

    Business Ambassador

    Solution Developer

AgilePM-Practitioner Question 9

AgilePM-Practitioner Question 9

Options:
Questions 10

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company's

bank. These scripts will be used

to test the link from the

company's website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website's

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

AgilePM-Practitioner Question 10

Options: