Free APMG-International AgilePM-Foundation Practice Exam with Questions & Answers | Set: 4

Questions 31

Which is a factor used in the 'change formula' (Beckhard and Harris)?

Options:
A.

Level of dissatisfaction with the status quo.

B.

Expected return on investment and benefits.

C.

The quality of the leadership.

D.

Elapsed time it will take to achieve the change.

APMG-International AgilePM-Foundation Premium Access
Questions 32

Which of the following statements is true?

Options:
A.

Project management is concerned with a wider context than product development.

B.

Project management addresses more complex problems than product development.

C.

Product development focuses primarily on who is involved and why it should be.

D.

Product development focuses on governance of the environment.

Questions 33

In which step of the Continuous Change Management Cycle should change actions be broken into smaller tasks?

Options:
A.

Discovery.

B.

Ideas.

C.

Prioritization.

D.

Action.

Questions 34

Considering the value statements in the Agile Manifesto which of the following

    Documents should only be created where they add value to the project

    Documents can be created but should never be used to form a contract

    It is vital that any documents created are visible to, and understood by, [stakeholders/team]

    High-level documents can be created early in a project to help support planning and understanding.

Options:
A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Questions 35

When initially creating MoSCoW priorities, what is the primary focus?

Options:
A.

Project priorities

B.

Project increment priorities

C.

Timebox priorities

D.

Iterative Development priorities

Questions 36

Which of the following roles may be substituted for a Scrum Master?

Options:
A.

There has been significant research and up front analysis

B.

The optimal solution has been designed and contracted

C.

The problem is unclear and change is inevitable

D.

The problem and solution are well defined and stable

Questions 37

Which of the phases in the AgilePM project lifecycle is optional?

Options:
A.

Feasibility

B.

Foundations

C.

Realization

D.

None

Questions 38

In a free format Timebox, when should reviews take place?

Options:
A.

During the Kick-Off phase

B.

Throughout the body of the Timebox.

C.

During the Close.Out phase

D.

After the Timebox has been completed

Questions 39

Identify the missing words in the following sentence.

Principles 1 –Focus on the Business Need suggests that every decision taken during a project should be [?] – to deliver what the business needs to be delivered.

Options:
A.

The responsibility of the Business Sponsor

B.

Share between all of the project roles

C.

Viewed in light of the overriding project goal

D.

Made collaboratively

Questions 40

Identify the missing words in the following sentence.

"It is unrealistic to expect that all four variables of time, cost, quality, and features can be fixed and controlled. It is necessary to allow for flexibility (contingency) in [ ? ]."

Options:
A.

the ‘variables’ of Time and Cost

B.

the ‘variables’ of Features and Quality

C.

the ‘variables’ of Individuals and Interactions

D.

at least one of these variables