Free APMG-International AgilePM-Foundation Practice Exam with Questions & Answers | Set: 3

Questions 21

Which of the following are recognized DSDM styles of Timebox?

1. Unstructured

2. Consolidated

Options:
A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

APMG-International AgilePM-Foundation Premium Access
Questions 22

Which approach is recommended for helping people through the 'change curve'?

Options:
A.

Actively involve line managers in listening and providing support.

B.

Recognize negative emotions as a sign that the change is being managed badly.

C.

Advise people not to discuss their problems with colleagues.

D.

Assume that everyone will eventually move on in time to deal with the change.

Questions 23

What is defined as "The means by which an organization increases involvement of its employees and other stakeholders with organizational change"?

Options:
A.

Engagement.

B.

Change Agent.

C.

Sponsor.

D.

Line Leader.

Questions 24

According to Pink, which three factors are key motivators for 'knowledge work'?

Options:
A.

Dissatisfiers, rewards, and safety.

B.

Autonomy, safety, and self-esteem.

C.

Hygiene factors, autonomy, and self-actualization.

D.

Autonomy, mastery, and purpose.

Questions 25

Which of the common Agile concepts, behaviors, and techniques composes fixed periods of time, at the end of which an objective has been met?

Options:
A.

Minimum viable product.

B.

Timeboxes (also known as sprints).

C.

Full transparency.

D.

Focus on frequent delivery.

Questions 26

How is Quality ensured during Evolutionary Development?

Options:
A.

By managing objectives in a fixed time period

B.

By continuous verification

C.

By understanding and managing priorities

D.

By facilitating session to enable a group to work to achieve an agreed goal

Questions 27

According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?

Options:
A.

During evolutionary development

B.

At the start of the project

C.

When the Business Advisor is available

D.

Whenever the level of solution quality is known.

Questions 28

In a free format Timebox, when should reviews take place?

Options:
A.

During the Kick-Off phase

B.

Throughout the body of the Timebox.

C.

During the Close.Out phase

D.

After the Timebox has been completed

Questions 29

Which of the following is an important way a change manager supports sponsors in their role?

Options:
A.

Prepare the change vision for them.

B.

Gain the commitment of other executive leaders.

C.

Offer them feedback and coaching.

D.

Protect them from the demands of line leaders.

Questions 30

Who is responsible for the application of Principle 8, Demonstrate Control?

Options:
A.

Collectively applied by the whole team

B.

The project-level roles

C.

Team Leader

D.

Project Manager