Free Adobe AD0-E903 Practice Exam with Questions & Answers | Set: 2

Questions 11

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?

Options:
A.

Log a risk as part of the project business case and identify it as a "schedule" risk.

B.

Log an issue on the project and explain that the completion date is at risk.

C.

Create a task in the project and set the Planned Completion Date for 2 weeks.

Adobe AD0-E903 Premium Access
Questions 12

AD0-E903 Question 12

What do the connector lines between tasks in a Gantt chart represent?

Options:
A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Questions 13

What are two characteristics of a Group in Workfront? (Choose two.)

Options:
A.

A Group can be tagged in an Update thread communication.

B.

A Group assignment is not required for a user.

C.

A Group can be associated with a Company or a Project.

D.

A user can be assigned as Group Administrator of a Group.

Questions 14

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

Options:
A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

Questions 15

How is the primary assignee of a task determined?

Options:
A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Questions 16

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

Options:
A.

Estimated Date

B.

Projected Date

C.

Planned Date

Questions 17

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Options:
A.

Visit the Reports page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month."

B.

Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select "month of year."

C.

Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month of year."

Questions 18

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

Options:
A.

Assigned To

B.

Assignments

C.

Assigned

Questions 19

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

Options:
A.

The next team member cannot start his task.

B.

No impact as the task is not overdue.

C.

The project shows an At Risk automatic condition.

Questions 20

Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

Options:
A.

Add a cross-project predecessor on the final milestone of Project 1.

B.

Add a cross-project predecessor on Task 1 in Project 1.

C.

Add a cross-project predecessor on the final milestone in Project 2.