Free Scrum SMC Practice Exam with Questions & Answers | Set: 2

Questions 11

Altas, Inc. has a project that consists of multiple Scrum Teams. A Scrum of Scrums is being organized to improve coordination among the teams. Who among the following facilitates a Scrum of Scrums?

Options:
A.

Chief Product Owner

B.

Chief Scrum Master

C.

Scrum Team Representatives

D.

Scrum Master

Scrum SMC Premium Access
Questions 12

Which process is NOT carried out as a part of the Implement phase?

Options:
A.

Create Sprint Backlog

B.

Conduct Daily Standup

C.

Create Deliverables

D.

Groom Prioritized Product Backlog

Questions 13

You are a Scrum Master on a project to construct a business park. The Scrum Team has just completed the Create Deliverables process. All of the following are outputs of this process, EXCEPT:

Options:
A.

The basement wing of the automated parking garage.

B.

Raw materials acquired for the next Sprint.

C.

An updated blueprint of the automated parking system for the next level.

D.

The application of seismic retrofits to reduce the risk of damage due to earthquakes.

Questions 14

Mark is a member of a Scrum Team responsible for testing the code in an ongoing Sprint. Andy, the Product Owner, reassigns him to another project that needs a tester. What should Mark do in a scenario like this?

Options:
A.

Inform the Product Owner of the situation, who may extend the deadline for the current Sprint.

B.

Inform the Scrum Master of the situation, who should assign Mark's current task to someone else in the team.

C.

Inform the Scrum Master of the situation, who may discuss the situation with Andy.

D.

Inform the Product Owner of the situation, so that Mark's incomplete task is moved to the next Sprint.

Questions 15

There are differences in how quality is managed in Traditional Project Management and Scrum approaches to project delivery. Which of the following statements is FALSE in this regard?

Options:
A.

In traditional project management, once the user clarifies their quality expectations, it is the Project Manager who defines those user expectations in measurable terms.

B.

In traditional project management, changes can be made only through a formal change management system.

C.

In Scrum, the Scrum Master and the Scrum Team collaborate and decide on the Acceptance Criteria for the User Stories.

D.

In Scrum, development of the product is carried out by the Scrum Team in short iterations called Sprints.

Questions 16

Which of the following statement(s) is/are true with respect to Change in Scrum projects?

I. The Scrum Master suggests changes in consultation with the Scrum Team.

II. The Scrum Master can recommend changes based on Retrospect Sprint Meetings.

III. Changes that are beyond the tolerance level of the Product Owner may need the assistance of the Scrum Master working with the Product Owner.

IV. The Scrum Master finalizes the formal Change Requests along with the Scrum Team.

Options:
A.

Only IV

B.

III and IV

C.

I and II

D.

Only I

Questions 17

Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?

Options:
A.

Eliminating all changes that may affect the quality of deliverables and processes.

B.

Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization by the Product Owner.

C.

Providing requests for changes in a project.

D.

Approving changes that are amended, removed, or added according to project requirements and communicating the same to the Scrum Team.

Questions 18

Which of the following activities is NOT executed during the Implement phase in Scrum?

Options:
A.

Daily Standup Meeting

B.

Updating the Product Backlog

C.

Release Planning Meeting

D.

Creating deliverables

Questions 19

During the Ship Deliverables process, in order to deploy Product Releases and coordinate this with the customer, the Product Owner and Scrum Master plan to have a Piloting Plan. How can they make it effective?

Options:
A.

By ensuring that the target deployment user base is specified in the plan

B.

By ensuring that security-related issues are specified in the plan

C.

By ensuring that guidelines for minimizing friction among employees are specified in the plan

D.

By ensuring that synchronization methods are specified in the plan

Questions 20

In Scrum, the Scrumboard is ______ at the end of each Sprint.

Options:
A.

Updated with new tasks and completed tasks

B.

Placed beside the new one to compare team velocities in Sprints

C.

Analyzed by the Scrum Master to understand project progress in that particular Sprint

D.

Reset or wiped off